GMV5 DC INVERTER VRF UNITS SERVICE MANUAL
25
IV. Onsite Review of Design Drawing
Installation personnel must carefully read and understand the design scheme and drawings
provided by engineering designers, and prepare detailed and feasible construction organization design
after reviewing the onsite status.
The following aspects of working drawing must be reviewed:
1. The loads of indoor and ODUs must match. The gross rated capacity of the IDU should be set to
a value that is 50% to 135% of the rated capacity of the ODU. In actual conditions, if the capacity of
concurrently operating IDUs exceeds 100% of the rated capacity of the ODU, the air conditioning system
fails to meet the requirement. Note: Configuration in excess of the capacity of the IDUs can affect the
comfort for users. The more the excess is, the lower the adjustment capacity of an air conditioning unit
will be. When the capacity exceeds 135% of the configured value, the system reliability can be affected.
Therefore, relevant regulations on capacity limit must be strictly followed.
2. The difference of level between an ODU and an IDU, and that between IDUs must be set within
the designed range.
3. Pipe bend for trapped oil is required for air pipe riser in the unit to ensure normal circulation in the
unit lubricating system.
4. The pipe diameter and manifold type in the cooling system must meet relevant technical
specifications.
5. The drainage method of unit condensate water must be reasonable; the pipeline slope must
follow the design requirement of unit.
6. The air duct direction and air flow are reasonably organized.
7. The configuration specifications, type, and control method of power cables should meet the
design requirement of unit.
8. The arrangement, total length, and control method of control line should meet the design
requirement of unit.
Note: Engineering construction personnel must strictly abide by the design drawings. If any design
cannot be implemented during construction and needs to be modified, contact the designer first for
approval and prepare a written document, that is, the design modification record.
Summary of Contents for GMV-224WM/B-X
Page 1: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL T1 R410A 50 60Hz GC201508...
Page 27: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 24...
Page 29: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 26 V Construction Organization Process...
Page 38: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 35...
Page 47: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 44 GMV 504WM B X GMV 560WM B X and GMV 615WM B X...
Page 156: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 153 low press ure air pipe...
Page 158: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 155 2 Low exhaust temperature protection E2...
Page 160: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 157...
Page 161: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 158 5 System refrigerant lacking protection U4...
Page 162: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 159 6 System high pressure ratio protection J8...
Page 163: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 160 7 System low pressure ratio protection J9...
Page 165: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 162 11 Pressure sensor fault...
Page 224: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 221 2 Model GMV 335WM B X Exploded View...
Page 242: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 239...
Page 248: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 245 Click Finish...
Page 254: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 251 Click Next Installing...
Page 255: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 252 Click Close...
Page 272: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 269...
Page 287: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 284 1 4 2 5 Communication Debug...
Page 297: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 294...
Page 304: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 301...
Page 307: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 304...
Page 349: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 346...
Page 375: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 372 JF00302751...