6
INSTALLATION
WINDOW REQUIREMENTS
1.
These instructions and installation parts are for a
standard double-hung window. It can be installed
with our without the expandable panels. Make sure the
opening is large enough for the size of unit
(figure A)
.
2.
The unit must be installed within 122 cm (48”) of a wall
grounded outlet. Do not use an extension cord.
3.
All supporting parts must be fixed to solid wood,
masonry or metal.
4.
Clear out the area where the unit is installed ; air inlets
and outlets must be free at all times.
N.B. :
For storm window, to make sure the unit will drain properly, attach a piece of wood
to the stool in order to allow the air conditioner to tilt toward outside.
Size of the window piece :
Width
- 2.5 cm (2”).
Length
- long enough to fit inside the window frame.
Thickness
- place a piece of wood on the stool to make it 1.3 cm (1/2”) higher than the
top of the storm window frame.
PREPARING THE AIR CONDITIONER
*
F
IX THE EXPANDABLE PANELS ON THE AIR CONDITIONER
BEFORE PLACING THE UNIT IN THE WINDOW
.
1.
Using 2 Phillips screws, install the top mounting
rail on the top of the unit casing
(figure B).
2.
Slide the left and right expandable panels into
the top and bottom mounting rails*
(figure C).
3.
Using 2 Phillips screws and screwing through
the holes on the panel edge, fix the expandable
panels onto each side of the unit
(
figure D).
A
B
Top mounting rail
Figure B
Figure A
Figure C
Expandable panel frame
Phillips screw
T
op mounting rail
Expandable panel
Phillips screws
BACK of the panel
Bottom rail
Top rail
Figure D
*The bottom mounting rail located under
the air conditioner is pre-installed in factory.