7.3.3. Procedure for installing GI sheet: (Optional)
7.3.3.1. Install the GI sheet 1meter away from the
sidewall of the Cocoon Lite.
7.3.3.2. Make sure that the GI sheet have wooden
posts or any equivalent that can withstand the
wind.
7.3.4. Requirement for GI sheet:
7.3.4.1.
Length varies on the capacity/measurement of the Cocoon Lite.
7.3.4.2.
Height is at least 80 centimeters.
7.3.4.3.
Gauge or thickness is at least 16.
7.4. LOADING
7.4.1. Check the moisture content of the
commodity to ensure the MC is at a safe
level.
7.4.2. Loading the bottom section:
a. Unfold the bottom section of the
Cocoon™ Lite and lay it out on the
prepared site.
b. Start piling the sacks on the bottom
section.
c. Put down the first four bags on every
corner of the Cocoon™ Lite (one for
each corner).
d. Make sure that the bottom section is
stretched by pulling the corners with
the bags. Stretching will reduce the
risk of rodent damage.
7.4.3. Required stack height:
a. Load the first layer of sacks in one
direction.
b. Continue adding layers in an
interlocking manner (crisscross), i.e.,
one layer on the top of the previous
layer.
c. Stack sacks to the corresponding
heights.
7.4.4. Mechanical loading of bagged commodity, optional for big sizes of
Cocoon™ Lite:
a. Stacking of grains involves diverse operations such as conveyor, forklift, or crane.
b. Operations provide continuous stacking without delays especially for outdoor installation.
Conveyor
Forklift
Crane