Meter Calibration
312776K
67
Meter Calibration
Calibrate the meter:
•
The first time the system is operated.
•
Whenever new materials are used in the system,
especially if the materials have viscosities that differ
significantly.
•
At least once per month as part of regular mainte-
nance.
•
Whenever a flow meter is serviced or replaced.
NOTE:
•
are
updated automatically after the calibration pro-
cedure is completed.
•
K-factor values on the screen are viewable only.
If needed, you can manually edit the K-factors
in
(page 38) or
(page 43).
•
All values on this screen are in cc, independent
of the units set in
.
•
The controller will use the active recipe
K-factors for meter calibration.
The active
recipe must be recipe 1 to recipe 60. Recipes
0 and 61 do not have K-factor values.
1.
Before calibrating meter A or B, prime the system
with material. For a color/catalyst change system,
make sure the color/catalyst valve is open.
2.
Shut off all spray or dispense devices connected to
the ProMix.
3.
Close both fluid shutoff valves and sampling valves.
4.
Place the beakers (minimum size - 250 cc) in hold-
ers. Put the sampling tubes into the beakers.
NOTE:
If tubes need replacing, use 5/32 in. or 4 mm
OD tubing.
5.
On the EasyKey, press the Setup
key to access
setup screens.
6.
Select
Recipe & Advanced Setup
and press the
Enter
key to select.
To avoid splashing fluid in the eyes, wear eye protec-
tion. The fluid shutoff valves and ratio check valves are
retained by mechanical stops that prevent accidental
removal of the valve stem while the manifold is pres-
surized. If you cannot turn the valve stems manually,
relieve the system pressure, then disassemble and
clean the valve to remove the resistance.
7.
Press the Right Arrow
key to select the
. Press
the Enter
key to select
either A Meter, B Meter, or Solvent. Press the Down
Arrow
key and select Start from the menu. Start
only one at a time.