Setup
1. Unpack the ram
2. Locate and Install the ram
3. Mechanical Setup
4. Connect hoses to electrical control panel
5. Connect electrical control panel to power source
6. Ground system
7. Select ADM settings
Unpack
1. Inspect the shipping box carefully for damage.
Contact the carrier promptly if there is damage.
2. Open the box and inspect the contents carefully.
There should not be any loose or damaged parts
in the box.
3. Compare the packing slip against all items in the
box. Report any shortages or other inspection
problems immediately.
4. Remove the unit from the skid and place it in the
desired location. See Location Requirements.
Location Requirements
1. Make sure there is sufficient overhead clearance
for the pump and ram when the ram is in the fully
raised position (approximately 110 in. (280 cm).)
2. If you are installing a vent hood, make sure there
is sufficient horizontal clearance for it. Locate the
ram near a connection to the factory ventilation
system.
3. Make sure the air regulators for the pump and
ram are fully accessible, with room to stand
directly in front of the pneumatic control panel
and the electrical control panel.
4. Make sure there is easy access to an appropriate
electrical power source. The National Electrical
Code requires 3 ft (0.9 m) of open space in front
of the electrical panel. Comply with all local
codes and regulations.
5. For hydraulic rams, locate the hydraulic power
supply in an area that has:
• easy access for servicing and adjusting the
hydraulic pressure on the supply unit.
• sufficient clearance for the hydraulic lines that
attach to the pump.
• easy access to read the hydraulic fluid level
gauge.
Install System
Refer to
for mounting and
clearance dimensions.
Follow all
Location Requirements, page 16
, when
selecting a location for the ram.
1. Apply 50 psi download pressure to ram.
2. Wrap the bar with the lifting sling.
3. Lift the system off the pallet using a crane or a
forklift and place in desired location.
4. Level the base of the ram, using metal shims.
5. Bolt the ram to the floor, using anchors that are
long enough to prevent the unit from tipping.
Install Hydraulic Power Supply
See the Ram manual for installation and dimensions.
16
334130A
Summary of Contents for 334130A
Page 10: ...Component Identification Electrical Control Enclosure Figure 3 Electrical Enclosure 10 334130A...
Page 57: ...Repair Figure 35 Inside of Electrical Control Enclosure 334130A 57...
Page 65: ...Parts Parts Therm O Flow 200 Supply Unit 334130A 65...
Page 68: ...Parts Electrical Module 68 334130A...
Page 69: ...Parts 334130A 69...