3 Installation
3.1 Mounting of the BlueBox
Before mounting the BlueBox check the scope of delivery for completeness:
(Example: minimum delivery scope without power supply and without sensor-/actuator module)
1.
BlueBox
2.
Manual BlueBox
3.
Configuration data sheet
4.
Drilling template
Be careful when choosing the location of the BlueBox, the location has to achieve the following properties:
•
rain-and sun-protected location
•
convenient location for a mobile network coverage, if the Blue Box is used with an optional modem
∗
The Blue Box should be mounted on a vertical surface.
The drilling template is used for mounting on a flat surface. Please choose suitable mounting screws and
dowels, which are suitable for the material of the mounting surface.
Remove the covers on both sides of the BlueBox.
Below you see the holes for the mounting screws.
Despite the construction of the BlueBox in protection class IP 65you have to install the measuring instrument
in a rain-and sun-protected site.
If this is not possible, the BlueBox must be mounted in an additional housing.
A great advantage of the BlueBox is their design flexibility. Therefore construction of installation will vary by
application. A description of the structure and assembly of the BlueBox can only serve as an example.
∗