COMMISSIONING
INTRODUCTION
Commissioning involves checking that all connections have been properly made and all hardware is functioning correctly.
This means the system must be initially installed in accordance with the previous section of this manual.
The panel default mode is ‘Installation mode’. In Installation Mode the green SYSTEM ON LED will flash on and off. The
panel will automatically detect and memorize all the devices connected to the loop in the system in “real time”. No extra
action is needed.
With the panel on default the system will be ready to operate and detect a Fire incident from the moment power is
switched on. Therefore, the system will be fully functional without any additional setting up. All further actions will tailor
it to the requirements of the specific installation at hand.
Once the connections and hardware have been checked it is possible to get the basic fire alarm system up and running
very quickly -
it is only necessary to have the system in Installation Mode for 120 seconds, then set the system to ‘Active
Mode’
. Programming of the system to provide more advanced functionalities is covered in the next section.
PANEL
Fire
- Indication of at least one Alarm in the Node Loops
Fault
- Indication of at least one Fault in the Node Loops
Pre
- Indication of at least one Pre-Alarm in the Node Loops
Sys
- Node System Fault Detected
5V
- Main Power Fault
COK
- 1s blinking = Installation Mode; Always ON = Active Mode