INSTALLATION - ELECTRICAL CONNECTION
Before connecting the plug into the power socket, follow these instructions:
IMPORTANT:
If a power socket needs to be installed or relocated, the work must be
done by a licensed electrician.
In New Zealand the cooking range must be connected to the supply by a supply cord
fitted with an appropriately rated plug that is compatible with the socket-outlet fitted to
the final sub-circuit in the fixed wiring that is intended to supply the cooking range.
INSTALLATION - GAS CONNECTION
These technical instructions have been prepared for use by Authorised persons.
THIS APPLIANCE MUST ONLY BE INSTALLED BY AN AUTHORISED PERSON –
PROOF IS REQUIRED FOR WARRANTY SERVICE CLAIMS.
The cooker has been manufactured with Natural Gas injectors fitted. For use with LPG
the cooker must be converted. The conversion kit is supplied. Information on converting
the cooker is included with these instructions.
The requirements of the local gas and electrical authorities must be adhered to,
consult AS5601 as appropriate.
Gas inlet fitting is 1/2” BSP (male) thread.
This appliance can be connected with rigid pipe as specified in AS5601 table 3.1.
This appliance is approved for hose connection in compliance with AS5601, clause
5.12.1.8. The flexible hose must comply with AS/NZS 1869 (AGA Approved), 10mm ID,
class B or D, between 1 – 1.2 m long and in accordance with AS5601 for a high level
connection. The hose should not be subjected to abrasion, kinking or permanent
deformation and should be able to be inspected along its entire length. Unions’
compatible with the hose fittings must be used and all connections tested for gas leaks.
• Theelectricalsupplyfortheuprightcookermustbea240Volt50Hz.
• Thefuseandelectricalwiringofthedwellingmustsupporttheloadoftheappliance.
• The3-pinplug,usedtoconnecttheelectricity,mustbeeasilyreachedwhenthe
upright cooker is in its installed position.
• Theuprightcookermustbeearthed.Connecttheuprightcookertoaproperly
earthed and rated power socket, as appropriate.
• Theflexiblecordoftheuprightcookermustnotbesubjecttodirectheatandmustbe
positioned after installation so that its temperature does not exceed 75°C.
The fixed consumer
gas
supply
outlet should be at
approximately the same height as the cooker connection
point, pointing downwards and approximately 150mm to
the side of the cooker. The hose should be clear of the
floor when the cooker is in the installed position. Ensure
that the safety chain is installed correctly so that the chain
prevents strain on the hose connections when the cooker
is pulled forward.
If the connection is for natural gas the test point pressure
should be adjusted to 1.00kPa with the wok burner
operating at maximum.
GAS CONNECTION
If installing for use with LPG ensure that an AGA approved
gas regulator suitable for a supply pressure of 2.75kPa is
part of the tank supply and the test point pressure is
adjusted to 2.75kPa.
-
There is an LPG conversion kit supplied with the cooker.
-
It is recommended that an isolating valve and union
be
fitted, to enable simple disconnection for servicing.
These
are to be in an accessible location.
-
Check connections are gas tight with soapy water or
other approved method.
- Under no circumstances use a naked flame in
checking
for leaks.
-
Check Gas Adjustments (refer
installation - gas
checks
and adjustments
).
-
REGULATOR PLACEMENT - We strongly advise to
locate the Natural Gas regulator close to the gas inlet
and away from the heat of the cooker. Regulator failure
due to heat exposure is not covered under warranty.
-
When satisfied that the upright cooker is operating
correctly, instruct the customer in its safe operation.
Ensure the customer understands fully by having
them
operate the upright cooker in all its functions.
N
AT
GAS
Natural Gas
LPG Gas
Gas Flow from floor
mounted tap with
regulator installed
Gas Flow
Flexible
hose
to cooker