Page 1: ...To help people embrace light air and space GV Standard Xvent Installation Manual...

Page 2: ...Mills Road Diss Norfolk IP22 4RG Registered in England No 2987024 VAT No 637 7241 26 01379 658300 info glazingvision co uk FM596998 EMS613885 Contents Section Description Page Introduction 3 Safety 4...

Page 3: ...dalone solo and integrated formats The Xvent has been designed and tested to BS EN 12101 2 2003 A variety of optional extras including a rain sensor thermostat remote control and building management s...

Page 4: ...ds Clients are wholly responsible for all lifting to get the product to the upstand ready for installation Where the client is going to be using manual handling as a means to move the product into pos...

Page 5: ...that the cables will be pulled too tightly and may result in damage to the product and or create additional work during maintenance visits Do not allow water to enter the product eg do not leave the...

Page 6: ...nclosed within the hardware box for each unit you should find at least the following Stainless steel woodscrews Plastic packers various sizes Low modulus silicone 3 Xvents have two coiled cables emerg...

Page 7: ...r to provide safe access during the installation works It will be necessary to work on the outside and therefore suitable provisions should be made for safe handling of the product including all relev...

Page 8: ...in until they stop against the base extrusion figure 2 4 Replace the clevis pins through the closest holes in the spreader bar 5 Loosen the adjustment fixings and slide the bracket until it is agains...

Page 9: ...y lift the product to the roof using strops underneath the wooden build frame spreader bars will be needed Glazing Vision recommends a 1 over 2 spreader arrangement but please consult with your liftin...

Page 10: ...and top and the majority of the weight still supported adjust the position of the product on the upstand so that the internal framework is equally spaced and aligned with the internal finishes 6 Caref...

Page 11: ...per the guidelines in the next section as the Xvent is a safety critical product this will need to be done by a Glazing Vision Engineer 13 Follow the Site QC document Interior Finishing Glazing Vision...

Page 12: ...nt position 140 Figure 8 identifies the screws that should be removed to disconnect the lid from the mechanisms These two screws should be removed from the mechanism on either side of the vent If the...

Page 13: ...he lid disconnected and secured in the open position some checks are required to proceed First check that the unit is receiving the correct power from the power supply unit PSU Use a multimeter to che...

Page 14: ...programming port RJ45 see figure 14 on the front side of the Rooflight with the RS485 dongle and using the Configuration Application import the settings of the controller and confirm it is set as an X...

Page 15: ...96998 EMS613885 1 Open the Xvent via the control switch to 45 2 Close the Xvent from 45 via the control switch 3 Open the Xvent to the 140 fire position using the fire panel 4 Close the Xvent from 140...