Step
1
Create a level base using Crusher Run Stone to accommodate the overall footprint
of the woodbox kit.
Prepare an area 3
'
6
"
wide x 2
'
6
"
deep.
Remove sod and vegetation.
Excavate/remove soft soil as required to provide level stone surface at a
minimum of 4
"
deep.
If soil under sod is hard, soil can be leveled out and used as a base material.
If required, use landscape blocks to retain stone base.
If installing optional hearth/knee wall, extend base as required.
(Base Section View)
Reference diagrams for creating a level base.
Undisturbed Ground
Existing Ground
Screed Stone Base Level
4
"
4
"
min. Crusher Run Stone
3
'
6
"
2
'
6
"
NOTE: All outdoor living kits can be installed directly on a properly prepared stone base. However,
for best performance and appearance, a concrete pad is recommended.
“Stacker 150” Woodbox (WBX-150) Assembly Instructions
P.O. Box 3547 / Johnson City, TN 37602 / 1-800-414-4661 / www.GeneralShale.com
Woodbox Outline
3
'
x 2
'
(Base Plan View)
FRONT
3
'6"
x
2
'6"
Crusher Run Base
(4
"
min. thickness)
3