22
NOTE:
It will be necessary to determine the order of “shedding” the
connected loads and connect the loads to the LSM in that order.
One is the highest priority and four is the lowest priority.
Perform functional tests in the exact order
presented in this manual, or damage to the
switch could be done.
IMPORTANT: Before proceeding with functional tests, read and
make sure you understand all instructions and information in this
section. Also read the information and instructions of labels and
decals affixed to the switch. Note any options or accessories that
might be installed and review their operation.
NOTE:
This test can be performed with the utility or generator con-
nected to the loads. However if the generator is supplying the
loads and is overloaded the controller may have already turned
off certain loads.
Depress the “ TEST “ button on the load controller. This function
will disconnect all loads controlled by the controller. The load
controller will then reconnect each load in a timed and staggered
manner as described in the Transfer Switch Owner’s Manual.
Following transfer switch installation and interconnection,
inspect the entire installation carefully. A competent, qualified
electrician should inspect it. The installation should comply
strictly with all applicable codes, standards, and regulations.
When absolutely certain the installation is proper and correct,
complete a functional test of the system.
(01
13(90)
,SX;EXIV
,IEXIV
2. If the exercise time or day ever needs to be changed, press
the escape key to access the main menu.
3. Press the left or right arrow key until ‘Edit’ is flashing and press
enter.
4. Press the right or left arrow key until the exercise time is
displayed and press enter.
5. Using the arrow and enter keys first set the exercise hour in
24 hour format, followed by the minute, and finally the day.
6. Once set, the generator will exercise each week at the same
time. Be sure to show the owners how to set the exercise
function for the day and time they want the unit to exercise.
it was enabled at the factory and no adjustment is needed.
Every installation has its own unique set of circumstances
and requirements. This booklet provides guidelines for basic
installations only and is not intended to cover all applications.
If there are any questions or concerns after carefully reading all
Appendix E
Summary of Contents for Air-cooled Generators
Page 25: ...23 Electrical Schematic Drawing No 0H6386 B Electrical Data ...
Page 26: ...24 Electrical Data Wiring Diagram Schematic Drawing No 0H6385 A ...
Page 27: ...25 Wiring Diagram Schematic Drawing No 0H6385 A Electrical Data ...
Page 28: ...26 Electrical Data Wiring Diagram Schematic 8kW Drawing No 0J2999 A ...
Page 29: ...27 Wiring Diagram Schematic 8kW Drawing No 0J2999 A Electrical Data ...
Page 30: ...28 Electrical Data Wiring Diagram Schematic 8kW Drawing No 0J2999 A ...
Page 31: ...29 Wiring Diagram Schematic 10 14kW Drawing No 0J3000 A Electrical Data ...
Page 32: ...30 Electrical Data Wiring Diagram Schematic 10 14kW Drawing No 0J3000 A ...
Page 33: ...31 Wiring Diagram Schematic 10 14kW Drawing No 0J3000 A Electrical Data ...
Page 34: ...32 Electrical Data Wiring Diagram Schematic 17 20kW Drawing No 0J3001 A ...
Page 35: ...33 Wiring Diagram Schematic 17 20kW Drawing No 0J3001 A Electrical Data ...
Page 36: ...34 Electrical Data Wiring Diagram Schematic 17 20kW Drawing No 0J3001 A ...
Page 37: ...35 NOTES ...
Page 38: ...36 NOTES ...
Page 39: ...37 NOTES ...
Page 40: ...Part No 0J4873 Revision B 06 29 11 Printed in U S A ...