background image

DIMENSIONS OF THE MAIN REPLACEMENT PARTS

EQUIPMENT

DIMENSIONS

LxWxH

WEIGHT

NOTE

mm

in

kg

lbs

Replacement BRM gradient coil assembly

on a shipping cradle/cart

902x2444x1420

35.5x96.1x55.9

1491

3287

 Initial gradient coil assembly is shipped

installed in the magnet.

Shipping/installation cart is used to install

re-placement coil assembly only.

The weight bearing structure of the site should support any additional weight of the main replacement parts
occurring during maintenance of the magnet, throughout the whole lifecycle of the MR.

Front view of the BRM Gradient

Side view of the BRM Gradient

2444

[96.2 in]

902

[35.5 in]

ROUTING

The customer is solely liable for routing of components from dock to final site.

GE

 must be able to move system components in or out with no need to uncrate or disassemble any of the

components. The entire passageway must be cleared, adequately lighted and free from dust.
The floor and it surfacing must be able to withstand the live load of components and handling equipment.
Floor surfacing must be continuous.
The customer must protect any fragile flooring surfaces.

MINIMUM SPECIFICATIONS FOR MAGNET ROUTING

Floor must be able to withstand a moving load of 5320 daN
Minimum Opening: Height: 2.5m (98.5 in), width: 2.5m (98.5 in)
Maximum slope: 30 degree

STRAIGHT PATH

(Rigging wheels required)

PATH WITH 90 DEGREE TURN

INSTALLATION AND DELIVERY ACCEPTANCE

A survey of the site established by the customer and 

GE 

Healthcare will

make the decision for the delivery time.

This survey of the site (a form is made available by 

GE

) is only to check if the

apparent conditions of the site allow the equipment to be delivered.
If the site is not ready, 

GE

 can delay the delivery time.

DELIVERY

Recommended minimum opening for side (wall) delivery : 2500 (width) x 2500 (height)

FRONT VIEW OF MAGNET

RIGHT SIDE VIEW OF MAGNET

2467

 [97.1 in]

2388

 [94 in]

1953

 [76.9 in]

2500

 [98.4 in]

2700

 [106.3 in]

This is only a partial list of items required for delivery of the magnet.  For a complete checklist refer to the

pre-installation manual referenced on cover sheet.

24/7 chilled water and 480v power for shield/cryo cooler

24/7 120v power for the magnet monitor

Phone lines for magnet monitoring and emergency use

Magnet room exhaust fan

Cryogen venting (if roof hatch, completed within 24 hrs)

Magnet anchors installed and tested

CRITICAL ITEMS FOR MAGNET DELIVERY

Date

Rev

/24

EN-MRI-TYP-SIGNA_EXPLORER-WEB.DWG

A

03/Aug/2018

SIGNA EXPLORER /SIGNA CREATOR

Typical

A8 - Delivery

10

Summary of Contents for SIGNA EXPLORER

Page 1: ...mplete set of final issue drawing GE cannot accept responsibility for any damage due to the partial use of GE final issue drawings however caused All dimensions are in millimeters unless otherwise spe...

Page 2: ...licable Power for MR compressor Chiller is available Ensure cryogen venting system is available for magnet connection Exhaust fan system is installed and operational per GE requirements Status of work...

Page 3: ...ned to the magnet room If not possible a barrier is recommended to prevent entry to the 5g field area 2 The spaces around above and below the magnet must be reviewed for effects of the 5g 3g 1g and 5g...

Page 4: ...contingent on a 72 in corridor width C 26 Minimum opening for is 43 in w x 82 in h contingent on a 96 in corridor width C 27 Counter top for equipment provide grommeted openings as required to route c...

Page 5: ...efine RF shield s inset according to provisions made by the RF Shield vendor Warning 5 Gauss line outside the Magnet room limits MAGNET ROOM CONTROL ROOM FRONT VIEW WITH MAGNETIC FIELD 6 4 3 2 1 1 3 1...

Page 6: ...ency generators Commercial laundry equipment Food preparation area Water cooling equipment HVAC equipment Major mechanical equipment room Credit cards watches and clocks Air conditioning equipment Fue...

Page 7: ...net cover is adjustable between 100 200mm 4 8 in D PP cover is adjustable between 300 400mm 11 8 15 7 in SYSTEM CABINET Top View PENETRATION PANEL Top View D D PENETRATION PANEL Front View Cut out cen...

Page 8: ...0 4 in 401 15 79 in 750 29 52 in 700 27 56 in 377 14 84 in 330 12 98 in 208 8 19 in GLOBAL OPERATOR CABINET GOC Center of Gravity SCALE 1 10 TOP VIEW FRONT VIEW SIDE VIEW 300 11 8 in PENETRATION PANEL...

Page 9: ...ravity GAS SUPPLY RETURN WATER OUT IN 232 9 13 in 450 17 72 in 103 4 06 in 276 10 87 in 153 6 02 in 450 17 72 in 800 31 5 in 153 6 02 in 153 6 02 in BLOWER BOX A Air in take clearance B Duct trim cove...

Page 10: ...ROUTING Floor must be able to withstand a moving load of 5320 daN Minimum Opening Height 2 5m 98 5 in width 2 5m 98 5 in Maximum slope 30 degree STRAIGHT PATH Rigging wheels required PATH WITH 90 DEGR...

Page 11: ...safety all removable items within the magnet room such as faucet handles drain covers switch box cover plates light fixture components mounting screws etc Must be non magnetic If you have a specific...

Page 12: ...ng 4 Structural wall backing for Magnet Rundown Unit 5 Structural wall backing for Main Disconnect Panel 6 Structural wall backing for Magnet Monitor 7 Floor levelness area for Systems Cabinet Date Re...

Page 13: ...ded to the structural elements and not to common screed for magnet anchoring table dock anchor hole VibroAcoustic Pad weight 8 kg 17 lbs each Seismic anchor holes 1346 53 in 673 26 5 in 250 9 8 in 175...

Page 14: ...supplied and installed by the customer or his contractors For complete design and requirements specifications and guidelines refer to the pre installation manual system cooling cryogen venting wavegu...

Page 15: ...xhaust Intake Vent MAGNET ROOM CONTROL ROOM RF Filter ON OFF Manual fan switches in parallel Ductwork Ductwork MAGNET ROOM VENTING REQUIREMENTS HVAC VENT REQUIREMENTS HVAC vendor must comply with Magn...

Page 16: ...ow 30 l min 8 gpm Temperature rise at maximum flow Temperature rise at minimum flow Maximum inlet pressure of Chiller Cryo Compressor 690 kPa 100 psi Minimum inlet pressure of Chiller Cryo Compressor...

Page 17: ...PIPE DETAIL MAGNET VENT ADAPTER Do not remove or modify the vent adaptor bolted to the magnet VENT PIPE 610 mm 24 in may be cut to a minimum of 100 mm 4 in VENTGLAS CONNECTOR WAVEGUIDE Additional pipe...

Page 18: ...10 63 4 52 31 17 8 22 56 68 2 26 15 58 4 11 28 34 10 in 250mm 0 20 0 6 1 0 03 0 68 0 55 3 79 0 82 5 65 0 27 1 86 0 04 2 83 20 40 6 1 12 2 0 07 1 58 0 82 5 65 1 51 10 41 0 41 2 83 0 75 5 17 40 60 12 2...

Page 19: ...n direct as possible otherwise may result in the need for greater than standard cable lengths refer to the interconnection diagram for maximum usable lengths point to point 8 Conduit turns to have lar...

Page 20: ...ephone lines network connection Duplex hospital grade dedicated outlet 120 v emergency single phase power 15a Duplex hospital grade dedicated outlet 120 v single phase outlet routed through RF filter...

Page 21: ...P SIGNA_EXPLORER WEB DWG A 03 Aug 2018 SIGNA EXPLORER SIGNA CREATOR Typical E3 Electrical Elevations 21 MAGNET ROOM EQUIPMENT ROOM 8 9 TBD TBD 5 4 7 9 9 8 CONTROL ROOM 5 4 3 2 TBD TBD TBD TBD TBD TBD...

Page 22: ...THE FLOOR NOT TO SCALE Removable coverplate DUCT ON THE WALL Date Rev 24 EN MRI TYP SIGNA_EXPLORER WEB DWG A 03 Aug 2018 SIGNA EXPLORER SIGNA CREATOR Typical E4 Electrical Details 22 CABLE MANAGEMENT...

Page 23: ...E EMERGENCY OFF BUTTONS ARE SUPPLIED WITH GE MDP OPTION EMERGENCY OFF BUTTONS ARE CUSTOMER SUPPLIED IF GE MDP OPTION NOT USED CIRCUIT BREAKERS ARE PROVIDED FOR PDU CRYO COOLER COMPRESSOR CHILLER GRADI...

Page 24: ...5 75m 13 94 51 67 ft 17 98 m 59 ft 9 56 m 31 ft 12 5 m 41 ft 12 8m 42 ft 17 4m 57 ft 2 55 16 13m 8 35 52 9 ft 12 2m 40 ft 21 00 m 68 ft 4 3 11 3m 14 1 37 1 ft GOC MAGNET ROOM CONTROL ROOM EQUIPMENT RO...

Reviews: