Chapter 4: Installation
Step 5: Fill the Gas-Liquid Separator
Figure 6: The Gas-Liquid Separator
, as needed.
1. Open the door of the Analyzer.
2. Disconnect the tube from the top barb on the left side of the gas-liquid separator (the barb marked
“NDIR Filter”). See
Figure 6: The Gas-Liquid Separator
3. Fill the squeeze bottle with deionized (DI) water or the best-quality water available.
4. Use the squeeze bottle to fill the gas-liquid separator through the center top barb until the center clear
tube of the gas-liquid separator is filled with water.
5. Reconnect the tube to the barb.
Figure 6: The Gas-Liquid Separator
Step 6: Install Input/Output, Cables, and Accessories
The Analyzer's Input/Output (I/O) board is located in the top of the Analyzer under the access cover. Remove the
cover. There are four terminal blocks on the I/O board, with TB1 located closest to the front of the Analyzer. From
front to rear the other terminal blocks are TB2, TB3, and TB4. Consult the tables in this section for a list of
N
OTE
:
Before installing any wiring inside the Analyzer, put on a grounding strap for ESD protection.
.
Carrier Gas
Sparger Outlet
Reactor Outlet
Gas-Liquid
Separator (GLS)
Waste
NDIR Outlet
NDIR Filter