INSTA LL ATION INSTRUC TIONS

Servicenter

 mini-unit substation

Three-phase 22.5 kVA models

Receiving
Upon receipt of shipment, examine the 
package for any damage that may have 
occurred in transit. While unpacking, 
examine the unit for broken, bent, loose 
parts, or other damage. If injury from 
outside sources is evident, file a damage 
claim with the transportation company 
and notify the nearest sales office.

Storage and handling
The storage area should be clean. Before 
placing the unit in service after a period of 
storage, be sure it is clean and dry by 
observing the instruction under 
“Installation”. The unit may be fork truck 
lifted or raised by the lifting holes located 
on the top core clamps under the 
transformer cover.

Installation preparation and mounting
If the interior moisture is evident by the 
appearance of rust, the unit should be 
dried. Megger readings of 10 Megohms 
minimum should be obtained before 
installation. Free circulation of air is 
essential for proper operation of the unit. 
The servicenter will perform at its rated 
output when surrounding air does not 
exceed 40 °C (105 °F) and adjacent 
structures permit free movement of 
cooling air. The unit must be mounted 
upright.

Connections

NOTE: Do not make or change 
connections while unit is 
energized!

The unit must be mounted upright. 
Reference should be made to the wiring 
diagram (Figure 1) when making 
connections.

A new grounding electrode conductor is to 
be connected to the neutral bar of the 
secondary in accordance with the National 
Electrical Code.

If a primary terminal strip is bonded to the 
enclosure by means of the neutral bonding 
screw, it may be removed for special 
applications.

Make certain that all connections are 
electrically tight to prevent joint heating. 
If aluminum cable is used, adequate 
preparation of the aluminum cable and 
protection of the joint is essential.

Secondary branch circuit breaker ampere 
ratings and branch circuit conductor sizes 
must be selected in accordance with the 
National Electrical Code.

The servicenter is factory connected on 
the primary side for the nominal rated 
three-phase delta connected input 
voltage. If the primary input voltage is 
other than nominal, the transformer taps 
may be adjusted in accordance with 
instructions provided with the 
transformer.

The primary main breaker and the 
secondary main breaker may be changed 
using breakers of equal voltage ratings 
and “equal to” or “lower” current ratings. 
However, the use of primary breakers with 
current ratings lower than those supplied 
may result in nuisance tripping. This is due 
to in-rush currents in the primary winding 
which occur when the transformer is 
energized.

NOTE: Primary and secondary 
breakers with current ratings 
higher than those supplied must 
not be used.

After all electrical connections have been 
made and the required branch circuit 
breakers installed, the inside metal cover 
plate must have the corresponding branch 
circuit breaker knockouts removed and 
the cover-plate reinstalled. Fasten the 
cover-plate in place, being sure that no 
cables are caught between the cover-plate 
and the framework. Also, ensure that all 
breakers are aligned with the knock-out 
holes in the cover-plate. Branch circuit 
positions should be recorded on the 
identification labels provided.