            Figure 2: Install Retainer to secure breaker 

See figure 3, load center fully assembled with kit 

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

         Figure 3: shows Kit fully assembled 
 

5.

 

Remove  the  backing  from  the  enclosed  "SERVICE 

DISCONNECT"  label  and  attach  it  to  the  dead 

front/shield besides the main circuit breaker opening. 
 

 

WARNING:

  Service  barriers  (A)  must  be  correctly 

installed  on  the  line  side  of  a  main  device  in  GE  load 
centers, and MSLC to ensure isolation from live parts. 

 

WARNING: 

Installing  an  incorrect  size  wire  than  the 

specified  sizes  for  each  circuit  breaker  frame  will  negate 
the  barrier  ability  to  protect  personnel  from  exposed  live 
components. 

 

Location 

Conductors 

Lug Hole  

10 AWG to 2/0 AWG Cu/Al 

      Table 1: Shows the allowable wire range for the barrier.

 

The wires must be stripped to the correct length to maintain 

isolation.  Strip the wire to a maximum of 0.595 inches. 

After stripping the wires to the required length, the wires can 

be installed as shown in Figure 4. The service barrier must be 

correctly  installed  to  maintain  electrical  isolation  from 

accidental  contact.  Torque  the  wires  according  the  torque 

specification on the breaker. 

 
 
 
 
 
 
 
 
 
 
 
    Figure 4: Stripped wire installed           
 

The strip wire length are measured to the scale provided on 

side of main circuit breaker, as shown on Figure 5. 

Some THQL (1p and 2p up to 60 Amps) are finger safe and do 

not require a Service barrier. See Figure 6. 

 

                 

      

 

    Barriers not required                        Barriers required 

Figure 6: Breakers Where Service Barriers Are Required 

Imagination at work 

GE Configured Solutions 

41 Woodford Ave.  

Plainville, CT 06062 

www.geindustrial.com 

To contact GE Industrial Solutions post sales service team, call 888-437-3765 

 

*INDICATES A TRADEMARK OF THE GENERAL ELECTRIC COMPANY AND/OR ITS SUBSIDIARIES. 

INFORMATION PROVIDED IS SUBJECT TO CHANGE WITHOUT NOTICE.  PLEASE VERIFY ALL DETAILS WITH GE.  ALL VALUES ARE DESIGN OR TYPICAL WHEN MEASURED UNDER LABORATORY CONDITIONS, AND GE MAKES 

NO WARRANTY OR GUARANTEE, EXPRESS OR IMPLIED, THAT SUCH PERFORMANCE WILL BE OBTAINED UNDER END-USE CONDITIONS

 

  These  instructions  do  not  purport  to  cover  all  details  or  variations  in  equipment  nor  do  they  provide  for  every  possible 

contingency that may be met in connection with installation, operation, or maintenance. Should further information be desired 

or  should  particular  problems  arise  that  are  not  covered  sufficiently  for  the  purchaser’s  purposes,  the  matter  should

  be 

referred to the GE Company. 

 

Figure 5: Max. Strip Wire Length.

 

Oval 

Square 

Main Circuit Breaker 

Position 2-4 or 1-3 only 

Retainer 

Barrier 