background image

 

© 2016 General Electric All Rights Reserved 

       

WARNING:  Hazard  of  electrical  shock  or  burn.    Turn  off      

power supplying this equipment before working inside 

General 

To  comply  with  the  National  Electrical  Code  and 

Underwriters  Laboratories,  the  breaker  retainer  kit  and 

service  barrier  must  be  installed  in  accordance  with  the 

information  contained  in  this  sheet  and  by  a  qualified 

electrical contractor and/or licensed electrician. 

Introduction 

This bulletin provides instructions for installing circuit breaker 

retainer and Service barrier to Model 6 PowerMark Gold

TM

 GE 

Load centers.  The retainer is used to secure a 2-pole branch 

breaker on the load center interior when the breaker is used 

as a back-fed main circuit breaker. And Service barriers are 

installed on the line side of the breaker. 

Contents per Installation 

 THQLRK4 - Main Breaker Retainer & Service Barrier Kit 

Description 

Qty

AUX. BREAKER RETAINER 

JAM NUT HEX 

THQL Lug Barrier 

LABEL 

 

NOTICE:

 These instructions do not purport to cover all 

details or variations in equipment or to provide for every 
possible contingency to be met in connection with the 
installation, operation or maintenance.  Should further 
information be desired or should particular problems arise 
which are not covered sufficiently for the purposes, the 
matter should be referred to the General Electric Company.  
These instructions are intended for use by qualified 
personnel only. 

Installation Instructions 

1.

 

Uninstall  the  Dead  front/shield  and  retain  the 

mounting screws. 

 

2.

 

Install the 2-pole back-fed main circuit breaker (D) in 

position 2-4 or 1-3 only. See the load center directory 

label or numbers stamped on the dead front/shield to 

locate position. 

 

Use only a General Electric type THQL or THHQL two-

pole circuit breaker. 

 

3.

 

     Insert  the  Service  Barriers  (A)  onto  line  side  of circuit 

breaker (D) as shown in Figure 1. Two Service Barriers 

included  with  the  kit,  need  to  assemble  to  both  the 

poles. 

 

 

 

 

 

 

 

 

 

 

 

 

        Figure 1: Insert Service Barrier onto Main Circuit Breaker 

 

4.

 

Install  the  retainer  (F),  over  existing  nuts  (E),  and 

secure  with  the  2  nuts  (G)  provided  with  the  kit. 

Tighten to 35 lb-in (4Nm). See figure 2 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

PowerMark Gold ™

 

Load Centers 

PowerMark Gold

TM

 Model 6 Breaker Retainer & Service Barrier Kit Cat# THQLRK4 

 

 

  DEH41481 Installation Instructions 

 