Chapter 6
Field Replaceable Units
Section 6.1
Overview
Detailed instructions for removing and replacing eXplore Locus SP components and assemblies
appear in this chapter.
6.1.1
Lockout / Tagout (LOTO) Instructions
NOTICE
The equipment
must be locked
out for most
procedures in
this chapter.
All energy sources for equipment on which work will be performed and on which injury could occur
due to unexpected energization, startup or release of stored energy shall be deactivated. This
includes opening electrical circuits, closing and bleeding pressurized hydraulics and pneumatics,
blocking springs or counterweights and discharging capacitors (for example).
1.
LOTO indicates that the energy source is Locked Out and that an Authorized Employee is
actively working on the machine, equipment, process, or circuit. LOTO is limited to one shift or
the amount of time the person is actively working on the system. If the job is not finished and
the system is not ready to be put back in use, the authorized person shall apply the Transition
LOTO or the Out of Service LOTO, whichever is appropriate for the situation.
2.
When applying LOTO the following six step process (which is described in detail in the training)
must be followed:
a.
Prepare for shutdown.
b. Shutdown machine or equipment.
c.
Isolate machine or equipment.
d. Apply lockout and tagout device.
e.
Isolate stored energy.
f.
Verify Isolation.
3.
Temporary removal of LOTO
and re-energization of a machine or equipment may be
performed when power is needed for testing or positioning. When testing you must:
a.
Ensure the machine is operationally intact.
b. Notify all Authorized or Affected Employees who are working on the equipment or
are in the area that the equipment is going to be tested and to move to a safe area.
c.
Verify controls are in the "off" position.
d. Remove LOTO Locks and tags.
e.
Energize and proceed with testing.
f.
After testing, de-energize, verify system isolation, and re-apply LOTO Locks and
Tags.
4.
When removing Lockout/Tagout the following steps must be followed:
a.
Communicate to all Affected Employees.
Summary of Contents for Healthcare eXplore Locus SP
Page 2: ...This page is intentionally left blank...
Page 12: ...GE HEALTHCARE DIRECTION 5158821 100 REVISION 3 EXPLORE LOCUS SP SERVICE GUIDE Page 12...
Page 13: ...GE HEALTHCARE DIRECTION 5158821 100 REVISION 3 EXPLORE LOCUS SP SERVICE GUIDE Page13...
Page 37: ...GE HEALTHCARE DIRECTION 5158821 100 REVISION 3 EXPLORE LOCUS SP SERVICE GUIDE Page37...
Page 228: ...GE HEALTHCARE DIRECTION 5158821 100 REVISION 3 EXPLORE LOCUS SP SERVICE GUIDE Page 228...