GE M
EDICAL
S
YSTEMS
D
IRECTION
2317229, R
EVISION
3
LOGIQ™ 180 B
ASIC
S
ERVICE
M
ANUAL
4 - 2
Section 4-2 - General Procedures
Section 4-2
General Procedures
4-2-1
Power On/Boot Up
NOTE:
After turning off the system, wait at least ten seconds before turning it on again. The system
may not be able to boot if power is recycled too quickly.
4-2-1-1
System Boot-UP/Shutdown
Purpose: This is a description on how to Shut Down/Power-UP the system.
CAUTION
SYSTEM REQUIRES ALL COVERS
Operate this unit only when all board covers and frame panels are securely in place. The
covers are required for safe operation, good system performance and cooling purposes.
NOTICE
Lockout/Tagout Requirements (For USA only)
Follow OSHA Lockout/Tagout requirements by ensuring you are in total control of the Power Cable
on the system.
Signed
Date
TAG
&
LOCKOUT