and the upper end of plug. If the space is narrow, it can be extended by pushing down the plug or 

raising the piston rod by hand-wheel operation. 

 

6)

 

Dismantle the plug (13) from the bottom of the body (10). 
Note: The disassembly is completed by dismantling the packings (6), packing spacer (8), lantern ring (9) 

and guide bushing (7). 

 

7)

 

Inspect for any damages to each component parts. 
Note: As the assembly procedure for packing box may vary with the type of valve, please refer to the 
respective assembly drawings. 

 

 

3.2.

 

Polishing the Valve Seat 

When the valve seat needs polishing, install the seat ring (12) and plug (13) from the bottom of the 

body (10), attaching them tentatively to the body hand-tight, lightly press the plug (13) against the 

seat side from the bottom of the body (10), hold the plug with a wrench applied to the wrench holder, 

and polish the seating surface. Do not polish the seating surface too hard, otherwise it may be 

damaged. When polishing the seating surface, apply a fine-grain, quality abrasive to it. Thoroughly 

clean the seating surface prior to reinstallation. 

 

3.3.

 

Reassembly 

Reassemble the valve according to the following procedure after having completed the necessary 

maintenance. 

Please note that new packings and gaskets should be prepared for re-assembly. 

 
1)

 

Clean all the gasket surfaces of the body and the seat ring. 

2)

 

Set the guide bushing (7) toward the packing box bottom of the body (10). 

3)

 

Insert the plug (13) from the bottom of the body (10). Set the seat ring without the gasket. Stand up 

the body. 

4)

 

Install the packings (6), packing spacer (8), and lantern ring (9), leaded by the stem of plug (13) and yet 

the amount of packings and the order of packings are specified by each valve. When installing the 

packings which have the cut ends, they have to be staggered 120 degrees with respect to each 

other. 

5)

 

Regarding the installation of the packing follower (4) and of packing flange (3), follow the reverse of 

the disassembly procedure. Refer to the section 3-1 – point 5. 

6)

 

Mount the actuator on the body. At this time, follow the reverse of the disassembly procedure. 

Refer to the section 3-1  - point 5. 

7)

 

Move down the piston until it stops whether by applying air pressure in the upper part of the actuator 

piston or by hand-wheel operation. 

8)

 

Couple the piston rod (19) to the plug (13) with the split clamp (18). When coupling, confirm that the 

threads of piston rod and plug are completely engaged with each split clamp. It will be useful that 

you were marking before disassembling. 

Lightly tighten the nut (16) or bolt (26) of split clamp at the position being completely engaged. 

9)

 

Raise the plug whether by applying air pressure to the piston bottom of the actuator or by hand-

wheel operation. At that time, the plug is kept away from the seating surface. And then rotate the 

plug at a half turn counterclockwise in order to get completely the seating force. You can use the 

record made at the time of disassembly to provide the seating clearance. 

Summary of Contents for Masoneilan 73000 Series

Page 1: ...GE Data Classification Public GE Oil Gas 73000Series Masoneilan Sweep Angle Control Valves Models XX 73471 Instruction Manual ...

Page 2: ...HE SITE AND THE PARTICULAR REQUIREMENTS FOR OPERATION OF OTHER EQUIPMENT AT THE SITE THESE INSTRUCTIONS DO NOT PURPORT TO COVER ALL DETAILS OR VARIATIONS IN EQUIPMENT NOR TO PROVIDE FOR EVERY POSSIBLE CONTINGENCY TO BE MET IN CONNECTION WITH INSTALLATION OPERATION OR MAINTENANCE SHOULD FURTHER INFORMATION BE DESIRED OR SHOULD PARTICULAR PROBLEMS ARISE WHICH ARE NOT COVERED SUFFICIENTLY FOR THE CUS...

Page 3: ...2 Installation _____________________________________________________ 6 3 Maintenance____________________________________________________ 6 3 1 Disassembly ______________________________________________ 6 3 2 Polishing the Valve Seat _____________________________________ 7 3 3 Reassembly_______________________________________________ 7 3 4 Packing Box_______________________________________________ ...

Page 4: ...nintended stresses on the product The specific operating conditions will also impact the useful life of the product Consult the factory for guidance on specific applications if required prior to installation Warranty Items sold by General Electric are warranted to be free from defects in materials and workmanship for a period of one year from the date of shipment provided said items are used accor...

Page 5: ...degraded process system performance that can lead to injury or death Total compliance with all DANGER WARNING and CAUTION notices is required for safe operation This is the safety alert symbol It alerts you to potential personal injury hazards Obey all safety messages that follow this symbol to avoid possible injury or death Indicates a potentially hazardous situation which if not avoided could re...

Page 6: ...o disassemble the valve it must be removed from the piping Bring a chain block over the valve to remove it from the piping for disassembly and reinstall it after reassembly 1 Run a strong rope through the actuator yoke and remove the valve retaining bolts from the piping while slightly pulling the valve upward If the valve is installed in a horizontal position also run a rope around the body so th...

Page 7: ...and the seat ring 2 Set the guide bushing 7 toward the packing box bottom of the body 10 3 Insert the plug 13 from the bottom of the body 10 Set the seat ring without the gasket Stand up the body 4 Install the packings 6 packing spacer 8 and lantern ring 9 leaded by the stem of plug 13 and yet the amount of packings and the order of packings are specified by each valve When installing the packings...

Page 8: ...wiring With the above re assembly is completed but you must confirm the valve function by checking the valve actuation valve opening etc prior to start up 3 4 Packing box Maintenance of the packing box is a routine work The sealing performance of packing is kept by compression of packing Compression is obtained by evenly tightening the packing flange stud nut 2 for the packing flange 3 but pay att...

Page 9: ... 2015 General Electric Company All rights reserved Masoneilan 73000 Series control valves Instruction Manual 9 4 Drawing and Parts References ...

Page 10: ...10 GE Oil Gas 2015 General Electric Company All rights reserved Notes ...

Page 11: ...11 GE Oil Gas 2015 General Electric Company All rights reserved Notes ...

Page 12: ... 55 7921 Moscow Phone 7 495 585 1276 Fax 7 495 585 1279 SAUDI ARABIA Phone 966 3 341 0278 Fax 966 3 341 7624 SINGAPORE Phone 65 6861 6100 Fax 65 6861 7172 SOUTH AFRICA Phone 27 11 452 1550 Fax 27 11 452 6542 SOUTH CENTRAL AMERICA AND THE CARIBBEAN Phone 55 12 2134 1201 Fax 55 12 2134 1238 SPAIN Phone 34 93 652 6430 Fax 34 93 652 6444 UNITED ARAB EMIRATES Phone 971 4 8991 777 Fax 971 4 8991 778 UNI...

Reviews: