After the installation of the processor unit is finished you can then proceed with the formulation tank unit.
1. Open the shipping box.
2. Remove packing and discard. Remove the loose items.
3. Remove the system from the shipping container. Unit is heavy and requires 2 people to lift it out of the box.
4. Place the formulation tank unit into the desired location.
5. Run 3/8” tubing from the RO Out on the processing unit to RO In (10 in “Formulation System Diagram” on page 4) on the
formulation unit.
6. Run the “Unit Connection Cord” from RO unit to the formulation unit (11 in “Formulation System Diagram” on page 4)
7. Plug in the power cord (“Installation Hardware” on page 5) to the formulation tank panel (12 in “Formulation System Diagram”
on page 4). Do not plug the unit into the wall outlet at this time.
8. Install the A Formula to the left side of the unit when facing the front. The location will be marked with a large A and have green
tubing fed to it. Install the tubing (3 in “Formula Installation & Replacement” on page 16) into the fitting by fully inserting the
tubing about 1/2” into the fitting.
9. Install the B Formula to the right side of the unit when facing the front. The location will be marked with a large B and have blue
tubing fed to it. Install the tubing (3 in “Formula Installation & Replacement” on page 16) into the fitting by fully inserting the
tubing about 1/2” into the fitting.
10. To connect the pressure tank to the formulation tank, reference the diagram below. The pressure tank does not need to be next
to the formulation tank, it can be placed anywhere before the first point of use.
11. Locate the tubing on the water out to your points of use.
12. Cut the tubing where you would like the tank to be and insert the 1/2’ equal tee ( #2 ).
13. Place the tank in a safe location.
14.
Teflon the top stem on the pressure tank and thread on the angled stop valve ( #4 ). Place the enlarger ( #3 ) into the angeled stop
valve ( #4 ).
15. Run the tubing from the 1/2” equal tee ( #2 ) to the enlarger ( #3 ).
16. Make sure that the angled stop valve ( #4 ) is in the on position. When it is on the blue valve handle should run parallel to the tubing.
NOTE: If the angled stop valve is left in the off position and the pump is turned on it will over pressurize the pump and cause damage
to the pump.
17.
Distribute out to your points of use from the Form Out (9 in “Formulation System Diagram” on page 4) fitting. The diagram on
“POU Connection Layouts” on page 7 will show a typical point of use setup with the provided fittings from the “Installation
Hardware” on page 5.
Installation is now complete. Follow the start up instructions on the following pages to complete the installation.
INSTALLATION INSTRUCTIONS
1
2
5
4
1 - 1/2” Equal Tee
2 - 1/2” Trunk x 1/2” Branch Tees
3 - 1/2” Tube x 3/8” Stem Enlarger
4 - 3/8” Tube x 1/4” FPT Tank Valve
5 - Pressure Tank
3
PAGE 8