18) If the pressure is oscillating, perform a fine adjustment by opening or closing the discharge valve.
19) Once the pressure has stabilized, open the vent valve by one-half turn and check the adjustment
accuracy.
20) Once the pressure regulation agrees with the desired value, you shall close the vent valve and
check the valve lock-up.
21) While we are testing the lock-up of the active valve, we recreate a scenario similar to a consumption
stop by the end customer, which is a normal process condition and, in such a case, the two valves
shall be closed as shown below: