190-01639-00
GSU 75 ADAHRS Installation Manual
Rev. 6
Page 5-1
5 POST INSTALLATION, CONFIGURATION, AND CHECKOUT
PROCEDURE
CAUTION
Be sure to check all aircraft control movements before flight is attempted to insure
that the wiring harness does not touch any moving part.
NOTE
The following procedures reflect a Garmin Integrated Flight Deck installation.
5.1 Function Selector Switches and Display
There are no operating controls or displays on the GSU 75.
5.2 Post-Installation Calibration Procedures
After mechanical and electrical installation of the GSU 75 AHRS and GMU 44 magnetometer have been
completed, prior to operation, a set of post-installation calibration procedures must be carried out.
Table 5-1 describes the necessary calibration procedures:
Table 5-1 Post-Installation Calibration Procedure Summary
Calibration
Procedure
Procedure Name
Procedure
Description
Installations Requiring Procedure
A-1
Pitch/Roll Offset
Compensation
Level Aircraft
Either procedure A-1 or A-2 is required
for all installations.
Procedure A-1 is
recommended.
A-2
Zero Pitch/Roll
Offsets by Manual
Entry
Manually enter
zeros for pitch/roll
offsets (pass-code
required)
This procedure should be used only if
leveling the aircraft is not feasible and
the AHRS is mounted to within 0.25° of
aircraft level reference
B
Magnetometer
Calibration
Compass Rose
Taxi Maneuver
All installations
This procedure should be repeated
following a removal or replacement of
the GMU 44 unit, or degaussing of the
area near the GMU 44 location.
C
Heading Offset
Compensation
Compass Rose
Alignment with
Magnetic North
Strongly recommended in installations
in which GMU 44 alignment is not
within 0.5° of aircraft forward
longitudinal direction
D
Engine Run-Up
Vibration Test
Validate vibration
characteristics of
installation
All installations
340095
The document reference is online, please check the correspondence between the online documentation and the printed version.