Commissioning and decommissioning
6.2.2 Decommissioning of the machine
a) Switch the machine off and allow it to cool down.
b) If available, close the cut-off device in the inlet and outlet pipes.
c) Disconnect the machine from the power supply.
d) Depressurise the machine:
Open the pipes slowly.
The pressure reduces slowly.
e) Remove the pipes and hoses.
f) Drain the condensate from the silencer (VLR 122).
g) Seal the connections for inlet and outlet stubs using adhesive foil.
See also chapter 3.2.1, page 11
6.3 Recommissioning
a) Check the condition of the machine (cleanliness, cabling etc.).
For installation see chapter 5, page 16