www.futurelight.com
23
1
Mount the truss bars to the truss via their center M20 eyelets and suitable steel ropes. Use one
steel rope and one secondary safety element per truss bar.
2
Interconnect the truss bars with their U profiles.
3
Mount the first display to each truss bar. For this, push the display’s bolts from below through
the truss bar and lock them by turning them by 90°. Further secure the displays with the vertical
and horizontal fixation screws.
4
Mount all other displays from top to bottom by fastening the bolts and fixation screws.
5
Make the power and data cabling (
➝
chapter 8).
6
Install the sending card and start the configuration with the PC program [LED Manager] (
➝
chapter 8).
Summary of Contents for PVS-7.62