Before unpacking the equipment rack, inspect the container (see
signs of shipping damage. Claims for shipping damage must be filed with the transportation
company in accordance with their published procedure.
Note:
A shipping label is located on the front of the equipment rack container. Compare this with the
shipping documents.
3
Is this the correct shipment for this location?
If YES:
If NO:
4
Using all data sheets and job engineering drawings, verify that the information matches the
installation site.
5
Using industrial shears, cut the two shipping bands from the container. See
for the location of the shipping bands.
After the last shipping band is cut, the top of the shipping container will fall away.
Figure 2-8: Example of an Equipment Rack in Shipping Container
r1252_
1
Revision 1, June 2009
Summary of Contents for FLASHWAVE 7500
Page 8: ...Revision 1 June 2009 ...
Page 10: ...Revision 1 June 2009 ...
Page 16: ...Revision 1 June 2009 ...
Page 362: ...Revision 1 June 2009 ...
Page 386: ...Revision 1 June 2009 ...