CHAPTER 3
Small Configuration
Checking Ground Resistance at the Optical/Tributary Shelf Power Input
3-107
FLASHWAVE 7500 Release 6.1
Equipment Installation
Fujitsu and Fujitsu Customer Use Only
FNC-7500-0061-200
Issue 1, May 2009
3
Use the DMM set for the ohms function or an ohmmeter to measure the resistance between
frame ground and each of the battery return points (A and B) on the shelf. The reading
should be very close to 0 ohms.
4
Is the reading close to 0 ohms?
If YES:
If NO:
Do not continue with
until the voltage source has been eliminated. For
technical assistance, call 1-800-USE-FTAC (800-873-3822).
5
Swap the DMM or ohmmeter leads between frame ground and battery return, and verify the
same reading as described in
.
This procedure is complete.
Revision 1, June 2009
Summary of Contents for FLASHWAVE 7500
Page 8: ...Revision 1 June 2009 ...
Page 10: ...Revision 1 June 2009 ...
Page 16: ...Revision 1 June 2009 ...
Page 362: ...Revision 1 June 2009 ...
Page 386: ...Revision 1 June 2009 ...