5 | Installation
20
M2050222_en | Installation instructions Lambdamat LM 1500 KOM
5.4 Positioning at the installation site
5.4.1 Moving the boiler in the boiler room
r
Position a lifting device with a suitable load-bearing capacity at the base frame.
r
Lift and transport to the intended position in the installation room.
Ä
Observe the minimum distances in the boiler room.
5.4.2 Operating and maintenance areas of the equipment
▪ The system should generally be set up so that it is accessible from all sides to allow
quick and easy maintenance!
▪ Regional regulations regarding necessary maintenance areas for inspecting the
chimney should be observed in addition to the specified distances!
▪ Observe the applicable standards and regulations when setting up the system!
▪ Comply with additional standards for noise protection!
(ÖNORM H 5190 - Noise protection measures)
D1
B1
B2
A1
C1
E1
A1
3,650 mm
B1
1,400 mm
B2
1,800 mm
(2,100 mm for dismantling the ash screw for maintenance tasks)
C1
Stoker: 2,240 mm
hydraulic slide-on duct: 3,000 mm
D1
900 mm
E1
5,100 mm