140.010-IOM (NOV 2019)
Page 12
IDSC EVAPORATIVE CONDENSERS
INSTALLATION
Figure 14: Upper casing section rigged
Figure 15: Basin section rigged
Figure 16: Rigging connections
BASIN SECTION
Remove the nuts from the shipping support so that when
the unit is lifted the shipping support detaches from the
unit, allowing for it to be removed.
The shipping support can be disposed of after the basin
section is lifted.
Figure 17: Nuts on shipping support
Figure 18: Basin shipping support nut removal
Secure 4 screw pin shackles through each of the 4 lifting
lugs.
Figure 19: Pin shackles at the lifting lugs
Lifting
lugs
WARNING
Do not use hooks to lift the unit.
Use the straps or chains to attach the spreader bar to the
basin section of the unit.