IN-GNC08
- 21 -
© Future Products Group
INSTALLATION
Regulations
GN SERIES REFRIGERATED WELL
-
INSTALLATION
Compliance
with Local
Requirements
It is very important that your drop-in refrigerated well assembly is installed
correctly and that the operation is correct before use. Installation must comply
with local electrical, health & safety and hygiene requirements.
Setting Up
GN SERIES REFRIGERATED WELL
-
INSTALLATION
Unpacking
Unpack and check the unit for damage and report any damage to the carrier
and supplier. Report any deficiencies to your supplier.
The well is supplied fully assembled, with the control panel mounted on the
main assembly.
Food dishes and supports may be packed separately.
Transport
After removal from the crate, the well assembly can be transported by fork-lift,
with the forks either under the base unit or under the top flange.
Site
Preparation
Ensure the well location and any joinery cut outs are made to the precise
measurements shown in the Mechanical Drawings. Position the well in its
allocated working position. Use a spirit level to ensure the well is level from side
to side and front to back. (If this is not carried out, water will collect in the well).
Well Assembly
Preparation
Remove all tapes, ties and packers, used to prevent movement during transit.
Lift out the food dishes, grills and divider bars.
Check that all plastic film protection has been removed from surfaces.
Grounding
WARNING: THIS APPLIANCE MUST BE GROUNDED TO EARTH
The grounding lead, in the mains cable, must always be connected to earth.
A binding post is also provided, to allow the cabinet to be bonded to a surge
grounding conductor or to adjacent equipment, should this be required.