Installing a NetIron MLX-4 Router
This section describes the steps you will perform to install a NetIron MLX-4 router:
•
“Preparing the Installation Site”
•
“Unpacking a NetIron MLX-4 Router”
•
“Chassis Lifting Guidelines for NetIron MLX-4 Routers”
•
“Installing a NetIron MLX-4 Chassis in a Rack”
•
“Installing NetIron MLX-4 Modules”
•
“Installing Power Supplies in a NetIron MLX-4 Chassis”
•
“Connecting AC Power to a NetIron MLX-4 Chassis”
•
“Connecting DC Power to a NetIron MLX-4 Chassis”
•
Preparing the Installation Site
Cabling Infrastructure
Ensure that the proper cabling is installed in the site.
For information on cabling, see “Installing Power Supplies in a NetIron MLX-4 Chassis” on page 3-9, “Attaching a
Management Station” on page 3-49, and “Connecting a NetIron MLX Series Router” on page 4-5.
Installation Location
Before installing the router, plan its location and orientation relative to other devices and equipment. For cooling
purposes, allow a minimum of six inches of space between the sides, front, and the back of the chassis and walls
or other obstructions. If a chassis is installed within a perforated enclosure, the perforations must have openings of
at least 60 percent of the surface.
NOTE:
This equipment is suitable for installation in a Network Telecommunication facility and where NEC
requirements apply. Additionally it may be installed in either a Common Bonding Network (CBN) or Isolated
Bonding Network (IBN). It is not intended for Outside Plant installations (OSP).
Unpacking a NetIron MLX-4 Router
The NetIron MLX-4 router ships with several items. Review the list below, and verify the contents. If any items are
missing, contact the place of purchase.
•
NetIron MLX-4 chassis with the appropriate number of switch fabric modules already installed in the slot
marked SF and a slot blank installed in all other module slots.
NOTE:
You must provide standard #12-24 pan-head screws for mounting the NetIron MLX-4 chassis into a rack.
•
CD-ROM containing software images and the user documentation (including this guide).
•
Warranty card.
•
A 115V AC power cable for each AC power supply you purchase from Foundry.
To unpack a NetIron MLX-4 chassis, follow these steps:
1.
Move the pallet to a staging area as close to the installation site as possible.
2.
Position the shipping carton with the arrows pointing up.
3.
Remove the strap that secures the shipping carton to the pallet.
4.
Remove the plastic cover and shipping carton.