4.5
Removing the control board (remote & EFC models)
4.5.1
Remove ash-pan, fret assembly / trim or fascia from the front of the fire.
4.5.2
Isolate the gas supply, disconnect the gas control valve to bulkhead
pipe and pilot / thermcouple connections to the pilot.
4.5.3
Pull controls sub assembly forward, disconnect wiring looms and
remove 4 off screws which secure the control board to the controls sub
assembly.
4.5.4
Replace in reverse order and carry out a gas tightness test.
4.6
Removing the control valve (remote & EFC models)
4.6.1
Remove ash-pan, fret assembly / trim or fascia from the front of the fire.
4.6.2
Isolate the gas supply, disconnect the gas control valve to bulkhead
pipe and pilot / thermcouple connections to the pilot. Pull controls sub
assembly forward, loosen and remove the three gas pipe retaining nuts
from the control valve and release the ends of the gas pipes from the
control valve body. Loosen and remove the thermocouple securing nut
from the end of the control valve.
4.6.4
Replace in reverse order and carry out a gas tightness test.
4.7
Removing the infra-red sensor (remote control models)
4.7.1
Remove ash-pan, fret assembly / trim or fascia from the front of the fire.
4.7.2
Isolate the gas supply, disconnect the gas control valve to bulkhead
pipe and pilot / thermcouple connections to the pilot.
4.7.3
Pull controls sub assembly forward, disconnect IR sensor lead from the
control board. Replace in reverse order and carry out a gas tightness
test.
4.8
Removing the battery holder & lead (remote & EFC models)
4.8.1
Remove ash-pan, fret assembly / trim or fascia from the front of the fire.
4.8.2
Isolate the gas supply, disconnect the gas control valve to bulkhead
pipe and pilot / thermcouple connections to the pilot.
4.8.3
Pull controls sub assembly forward, disconnect battery holder / lead
from the control board. Replace in reverse order and carry out a gas
tightness test.
26