3 | Assembly and Starting Operation
FISCHER Mess- und Regeltechnik GmbH
10 / 20
BA_EN_DE23
3.3.2 3-wire connection (0 ... 10 V)
supply
P1
+Sig1
-Sig1
+U
b
-U
b
channel 1
1
3
+
-
+
4
+U
b
-U
b
P2
+Sig2
-Sig2
channel 2
+
-
+
2
output1
output2
(~)
(~)
Fig. 8:
Electrical connections
Fig. 9:
M12 connector 4pol
1 channel version
Pin Description
Cable colour
1
Supply
(+)(~) +U
b
brown
2
white
3
Supply
(-)(~) -U
b
-Sig
blue
4
Output
(+)
+Sig
black
A
Coding
2 channel version
Pin Description
Cable colour
1
Supply
(+)(~) +U
b
brown
2
Output 2
(+)
+Sig2
white
3
Supply
(-)(~) -U
b
-Sig1 / -Sig2
blue
4
Output 1
(+)
+Sig1
black
A
Coding
3.4 Commissioning
A prerequisite for commissioning is correct installation of all electrical supply
lines and the pressure lines. All connections are arranged so that there are no
mechanical forces acting on the device.
CAUTION
Leak test
The pressure lines need to be checked for leaks before commissioning.
The device switches into normal mode as soon as the device is connected to a
power supply.