F300-10-00                                                                                                   7                                                                                              I56-0020-004R

[9.2.2] Alarm Tests
[9.2.2.1] M02-04-00 Magnet Test

1. Place the painted surface of the magnet onto the TEST locator
    on the bottom of the detector housing (Figure 11).
2. Verify system control panel alarm status and control panel execution of
    all intended auxiliary functions (i.e. fan shutdown, damper control, etc.)  
3. The detector is self-restoring when the magnet is removed.
    Verify that the system control panel has reset.  

[9.2.2.2] RTS451/RTS451KEY Remote Station Test

The RTS451/RTS451KEY Remote Test Station facilitates test of the alarm
capability of the duct smoke detector. These accessories provide the
stimulus to initiate an alarm condition at the detector. The detector is
self-restoring when the accessory test stimulus is removed. 
Verify that the system control panel has reset.   

[9.2.3] Sensitivity Tests

Notify the proper authorities that the smoke detector system is undergoing maintenance, and that the system will tempo-
rarily be out of service. Disable the device or system undergoing maintenance to prevent unwanted alarms and possible 
dispatch of the fire department.

[9.3] Maintenance of Duct Smoke Detectors
[9.3.1] Air Filters

1. Turn off power to the system.
2. Remove and inspect sampling tube filters.
3. If filters are heavily coated with dirt, replace them with new filters (p/n F36-09-11). If they are not heavily coated, use 

a vacuum cleaner or compressed air nozzle to remove dust, then reinstall the filters. 

[9.3.2] Photo Detector Boards 

1. Remove the screen by gently grasping on each side and pulling straight off
2. Lift the photo chamber in the same fashion. Vacuum the screen and cover. Use clean, compressed air to loosen and 

blow out any remaining debris. Replacement screens (p/n S08-39-01) are available.

3. Vacuum photo chamber, then use clean compressed air to blow area clean.
4. Replace the chamber by pressing it onto the base. Press the screen into place. It should fit tightly on the chamber. 

[10] Board Replacement
[10.1] Sensor Board Replacement

1. Remove the two sensor board mounting screws.
2. Pull gently on the board to remove it. 
3. To replace the board, align the board mounting features, holes, and the interconnect terminals. Push the board into 

place.

4. Secure board with the two mounting screws.

[10.2] Power Board Replacement

1. Disconnect wiring from the terminal block.
2. Remove the two power board mounting screws.
3. Pull gently on the board to remove it. 
4. To replace the board, align the board mounting features, holes, and the interconnect terminals. Push the board into 

place.

5. Secure board with the two mounting screws.
6. Re-connect wiring to terminal block.

Figure 11. Testing detector alarm:

F300-10-00                                                                                                   2                                                                                              I56-0020-004R

WARNING

LIMITATIONS OF DUCT DETECTORS 

WARNING

The  National  Fire  Protection  Association  has  established  that  DUCT  DETECTORS  MUST  NOT  BE  USED  AS  A 
SUBSTITUTE FOR OPEN AREA DETECTOR PROTECTION as a means of providing life safety. Nor are they a substi-
tute for early warning in a building’s regular fire detection system.

It is strongly recommended that the user read NFPA Standards 90A, 72, and 101.

WARNING

This device will not operate without electrical power. Fire situations may cause an interruption of power. The system 
safeguards should be discussed with your local fire protection specialist.

WARNING

This device will not sense smoke unless the ventilation system is operating.

WARNING

In order to function properly, this detector must be installed according to the instructions. Do not exceed the electrical or 
ambient specifications or the detector will not function properly. This detector must be protected from the elements.

INSTALLATION SEQUENCE

Step 1.     Verify duct air flow direction and velocity ......................................................................................................... 2
Step 2.     Drill the mounting holes ................................................................................................................................... 2
Step 2.1   Install the sampling tube for ducts less than 1

1

2

 

feet wide............................................................................... 2

Step 3.     Secure the detector housing to the duct .......................................................................................................... 3
Step 4.     Install the sampling tube for ducts greater than 1

1

2

 

feet wide ......................................................................... 3

Step 4.1   Installation for ducts greater than1

1

2

 

feet but less than 8 feet wide  ............................................................... 3

Step 4.2   Installation for ducts more than 8

 

feet wide   ................................................................................................... 4

Step 5.     Install the filters ................................................................................................................................................ 4
Step 6.     Field wiring ....................................................................................................................................................... 4
Step 7.     Perform detector check .................................................................................................................................... 5
Step 8.     Install the cover ................................................................................................................................................ 5
Step 9.     Detector Maintenance and Test Procedures.................................................................................................... 5

[1] Verify Duct Air Flow Direction And Velocity

The D350P duct smoke detector is designed to be used in air handling systems having air velocities of 500 to 4000 
feet per minute. Be sure to check engineering specifications to ensure that the air velocity in the duct falls within these 
parameters. If necessary, use a velocity meter to check the air velocity in the duct.

[2] Drill The Mounting Holes

Remove the paper backing from the mounting template supplied. Affix the template to the duct at the desired mounting 
location. Make sure the template lies flat and smooth on the duct. Center punch holes A and B. Drill the holes as indi-
cated on the template.

[2.1] Sampling Tube Installation for Ducts Less Than 1

1

2

 Feet Wide 

(see Figure 2)

1. Remove the front cover.
2. Slide the plastic sampling tube into the housing bushing and extend it 

the full width of the duct.

3. Align  the  holes  in  the  bushing  with  the  holes  in  the  sampling  tube. 

Secure with the #8 self-tapping screw into the bottom of the permanent 
tube. ( Shown in figure 2. ) 

NOTE: 

The sampling tube end cap is critical to the proper operation of 

the duct smoke detectors. The end cap is needed to create the proper 
air flow to the sensor of the duct smoke detector.

NOTE:

For ducts greater than 1

1

2

 feet in width, refer to sections [4], [4.1] 

and [4.2].

Figure 2. Plastic sampling tube 
connected to duct smoke detector

Summary of Contents for D350P

Page 1: ...y may fail at any time Any smoke detector fire alarm equipment or any component of that system which fails shall be repaired or replaced as soon as possible F300 10 00 1 I56 0020 004R Fire Lite Alarms Inc One Fire Lite Place Northford CT 06472 203 484 7161 Before installing detectors please thoroughly read the NEMA Guide for Proper Use of Smoke Detectors in Duct Applications which provides detaile...

Page 2: ...NS OF DUCT DETECTORS WARNING The National Fire Protection Association has established that DUCT DETECTORS MUST NOT BE USED AS A SUBSTITUTE FOR OPEN AREA DETECTOR PROTECTION as a means of providing life safety Nor are they a substi tute for early warning in a building s regular fire detection system It is strongly recommended that the user read NFPA Standards 90A 72 and 101 WARNING This device will...

Page 3: ...ow Make sure the sampling tube is mounted so that the arrow points into the air flow see Figure 4 Figure 5 shows the various combinations of tube mounting configurations with respect to air flow Mounting the detector housing in a vertical ori entation is acceptable provided that a metal sampling tube is used and the air flows directly into the sampling tube holes as indicated in Figure 4 4 1 Insta...

Page 4: ... performed inside the air duct Sampling of air in ducts wider than 8 feet is accomplished by using the ST 10 sampling tube If the tube is shorter than the width of the air duct install the end cap into the sampling tube as shown in Figure 4 and support the end opposite the duct smoke detector Install the sampling tube as follows 1 Drill a 3 4 inch hole in the duct directly opposite the hole alread...

Reviews: