Step 1: Unpack and ensure all components are correct and undamaged
•
Appliance.
•
Box of firebed mediums.
•
Flue kit.
Step 2: Install plinth (if required)
•
If the appliance is to sit on a plinth, ensure it is capable of
supporting a 150kg load.
•
There is no clearance requirement for the base of the appliance.
It may safely sit directly upon combustible (eg. timber)
and non-combustible (eg. concrete) materials.
Step 3: Install appliance into position
•
Before installation, confirm all minimum clearances
from the outside surfaces of the fire to the surrounding
enclosure is no closer than100mm from combustible
materials and non-combustible materials.
•
The exception to these minimum clearances is the base, the base can
safely sit directly upon combustible (eg. timber)
and non-combustible (eg. concrete) materials.
•
The appliance is supplied with a 1000mm long braided stainless steel gas
hose with a male gas bayonet connector that will plug into a gas bayonet
socket (gas bayonet socket not supplied). Refer to appropriate
‘The Fire Dept.’ product specification for
specific gas bayonet location requirements.
•
The appliance is supplied with a 1000mm long electrical cable and 3 pin plug that will plug into the electrical
wall socket (electrical wall socket not supplied). Refer to appropriate
‘The Fire Dept.’ product specification for
specific gas bayonet location requirements.
•
Locate appliance into position and ensure that it complies with the minimum clearances required (100mm for
combustibles) to the surrounding enclosure. The exception to these minimum clearances is the base, the
base can safely sit directly upon combustible (e.g. timber) and non-combustible (e.g. concrete) materials,
refer to the appropriate appliance specification for the correct clearance requirements. Ensure the framing is
capable of supporting a 150kg load.
•
The base has 2 x 10mm holes at the back of each side.
•
Mark out and drill fixing holes through the 10mm holes in the base. Ensure holes are drilled in the centre of
the holes. Clear out any debris from drilling.
•
Ensure the appliance is level and pack up corners to suit where necessary. Fix bolts / screws into floor.
Check and ensure unit is level.
•
If the electrician and/or gas fitter is available at this stage the electrical supply and gas supply can be
connected and tested/commissioned (see steps 5 & 6).