Fimer UNO-DM-3.3-TL-PLUS-US-SB-RA-Q Quick Installation Manual Download Page 5

5

8.  AC Output connection

 WARNING – 

B

To prevent electrocution hazards, open and lock 

out the external AC disconnect switch before connecting the AC 

conductors, and any time the AC wiring box cover is to be removed. 

Proper PPE is required. AC output overcurrent protection is not 

provided with the inverter; it is the responsibility of the end user to 

provide overcurrent protection for the AC output circuit. To reduce 

the risk of fire, connect only to a circuit provided with an overcurrent 

protection in accordance with the NEC (ANSI/NFPA 70). The inverter 

must be connected only to a dedicated branch circuit provided with 

the maximum branch overcurrent protection device (OCPD) listed in 

the technical data sheet at the end of this document. Size conductors 

per the NEC, Article 310 - use 90°C copper wire only; conductors 

must be sized according to operating temperature range and 

continuous current ratings. The AC grid wiring is connected through 

the inverter switchbox. AC output wire must be listed PV wire rated 

minimum 600V.

• Run an approved raceway between the inverter and external AC 

disconnect switch.

• Pass the AC wires throught the openings dedicated to the AC conduit.

 ATTENTION – 

A

When complete, seal conduit with water-tight fittings 

to maintain the NEMA type 4X enclosure rating. Installer should 

follow conduit manufacturers’ guidelines and best practices.

• Determine which AC output is applicable for the inverter model being 

installed. The AC wiring connections based on the AC grid type are shown 

in the table (also found on a label in the wiring box).

208V~

3PH -

240V~

SPLIT-PHASE

GRID ST

AND

ARD

TYPE DE RÉSEAU

TERMINAL

BORNE

WIRE

CÂBLE

L2

L1

N

L1

L3

L2

1

L1

2

L2

3

-

CAUTION

This is a single phase inverter. Use the wiring schemes shown on the
table below when a different grid standard is used. Refer to the
instruction manual to properly set the inverter grid standard from the
front panel display. Use 90°C copper wire only. Refer to the instruction
manual for wiring instructions.

ATTENTION

Ceci est un onduleur monophasé. Utilisez les schémas de raccordement
ci-dessus si le réseau est spécifique. Réferez-vous au manuel
d'installation pour sélectionner via l'afficheur frontal le code pays
adéquat. Utilisez seulement câbles en cuivre 90 °C.
Consulter le manual d'installation pour les instructions de câblage.

AWG# 4 - 8

1

L1

2

L2

3

N

• Connect wiring to the numbered terminals based on selected grid type. 

AC wiring terminals are spring pressure type and accommodate a wire 

size range of 20-6 AWG. 

• Connect the protective earth (PE) cable to wiring box busbar 

(16)

.  Screws  

the cable (max 4 wires 8AWG to 4AWG, copper) with 

2.0Nm (1.5ft-lb)

 

torque.

CAUTION

ATTENTION

REFER TO LOCAL CODE

FOR WIRE SIZE

FAIRE RÉFERENCE À LA

LÉGISLATION LOCALE POUR

LA DIMENSION DU CABLE

-IN1

+IN1

-IN2

+IN2

1

2

3

-RSD

+RSD

 WARNING – 

B

The default 240V split-phase connection requires 

the grid Neutral to be connected to the inverter for proper operation. 

Before connecting the inverter to the grid, the grid type must be 

selected during the commissioning phase. If several inverters are 

installed to a three-phase AC grid, always distribute the inverters 

between the phases in order to reduce power imbalance between 

the phases.

• When all connections are complete, reinstall the front covers and tighten 

the cover screws with 1.5Nm (13.2 in-lbs) torque.

9.  User Interface

LEDs 

, in various combinations, may show the status conditions or perform 

complex actions to be explored by consulting the product manual.

LEDs (06)

POWER Green

Solid when the inverter is working correctly. 

Flashes when checking the grid or if there is 

insufficient sunlight.

COMM

Green

Operation status of wireless communication line:

Blink Red

: Communication error (no communication 

available)

Green

: Communication OK

ALARM

Yellow

The inverter has detected an anomaly. The 

anomaly is shown on the “EVENTS” section of 

the internal webserver.

WLAN

Multicolor

Communication type and quality of the wireless 

communication signal (for “Station Mode”):

-  Blink Blue: Wireless board is working in Access 

Point mode (AP Mode)

- OFF: No signal

- Blink Red: Low signal strenght

- Blink Yellow: Medium signal strenght

- Blink Green: High signal strenght

GFI

Red

Ground fault on the DC side of the PV generator. 

The error is shown on the “EVENTS” section of 

the internal webserver.

POWER

COMM

ALARM

WLAN

GFI

06

10.  Commissioning

 ATTENTION – 

A

Before proceeding with commissioning, make sure 

you have carried out all the operations and checks indicated in the 

previous sections of this quick installation guides, and verify that the 

inverter cover 

(05)

 was properly closed!

  READ THE MANUAL  – 

E

Refer to the product manual for further 

information about the configuration and the use of the functionality 

of the internal Webserver. Consult the product manual for more 

information.

Commissioning and configuration of the inverter can be made using a 

wireless capable device such as a smartphone, tablet or laptop.

The steps for commissioning are listed below:

• Set the inverter’s DC disconnect switch 

(16)

 and any external DC switches 

to “ON” position: If the input voltage applied to one of the two input channels 

is greater than the minimum starting voltage, the inverter will start up.

 ATTENTION – 

A

The inverter is powered ONLY by the voltage coming 

from the photovoltaic generator: the presence of grid voltage alone IS 

NOT SUFFICIENT to allow the inverter to power up. If an RSD device 

is installed on the plant, the inverter will power-up only if both AC and 

DC are supplied!

• Set the external AC disconnect switch downstream to the inverter to “ON” 

position.

10.1  Pre-commissionig phase 1 - Connection to 

the local Wi-Fi network

DEVICE USED: TABLET/SMARTPHONE

Once powered, launch a QR reader for mobile 

and SCAN the QR code marked with 

 

 

SN WLAN: SSSSSSSSSS
PN WLAN: PPP.PPPPP.PP
MAC: XX:XX:XX:XX:XX:XX

SN Inverter: SSSSSSSSSS

MAC: XX:XX:XX:XX:XX:XX

PK: KKKK-KKKK-KKKK-KKKK

Remove and apply 

on the Quick

installation guid

e

 on 

the label on the right side of the inverter and 

connect to inverter network (tap connect).

The name of the Wi-Fi network created by 

the system, that the connection should be 

established with, will be:

ABB-XX-XX-XX-XX-XX-XX 

(where the X is the MAC address) 

After this step wait 10 seconds to allow the 

WLAN connection

 

 

SN WLAN: SSSSSSSSSS
PN WLAN: PPP.PPPPP.PP
MAC: XX:XX:XX:XX:XX:XX

SN Inverter: SSSSSSSSSS

MAC: XX:XX:XX:XX:XX:XX

PK: KKKK-KKKK-KKKK-KKKK

Remove and apply 

on the Quick

installation guid

e

Summary of Contents for UNO-DM-3.3-TL-PLUS-US-SB-RA-Q

Page 1: ... product manual from www fimer com Choose the correct country string inverters single phase choose the product and proceed to the download section Read and follow all safety and installation instructions to avoid disabling any safety features or making the warranty invalid APPLY HERE THE WIRELESS IDENTIFICATION LABEL ...

Page 2: ...ions 1 this device may not cause harmful interference and 2 this device must accept any interference received including interference that may cause undesired operation 2 ModelsandInverterComponents This installation guide covers 4 inverter models of different power levels 3 3 kW 3 8 kW 4 6 kW and 5 0kW For each model the following variant is available UNO DM 3 3 TL PLUS US SB RA Q UNO DM 3 8 TL PL...

Page 3: ...ting 6 in 4 in 4 in 8 in NO OK NO OK OK OK OK OK OK OK OK 5 MAX 5 MAX NO NO NO OK NO OK OK OK OK OK OK OK OK ATTENTION A Do not block access to the external AC and DC disconnects NOTE D Please refer to the warranty terms and conditions and avoid voiding the warranty with improper installation 4 Mounting Instructions Mount the inverter following the step by step procedure below ATTENTION A Do not r...

Page 4: ... This is the responsibility of the installer WARNING B Confirm that the maximum PV array short circuit current for each DC input channel is within the inverter specification see table in Section 14 Array equipment grounding must be installed per the requirements of the NEC and is the responsibility of the installer A configuration program that can help to correctly size the photovoltaic system is ...

Page 5: ...phases in order to reduce power imbalance between the phases When all connections are complete reinstall the front covers and tighten the cover screws with 1 5Nm 13 2 in lbs torque 9 User Interface LEDs in various combinations may show the status conditions or perform complex actions to be explored by consulting the product manual LEDs 06 POWER Green Solid when the inverter is working correctly Fl...

Page 6: ... vary for reasons connected to the wireless home router setup for example a very brief DHCP lease time If verification of the address is required it is usually possible to obtain the client list and the corresponding IP addresses from the wireless router administration panel If the inverter loses the connection with the home wireless network it is available accessing the Wi Fi network ABB XX XX XX...

Page 7: ...red by NFPA 70 Article 690 11 is provided by the inverter The AFD performs a self test when the system is started If the self test results are OK the inverter will continue to AC grid connection If a potential problem on the AFD board is detected the self test will result in error E053 During normal operation the input current is continually measured and analyzed If a DC arc fault is detected duri...

Page 8: ...ported by the inverter is a function of the operating grid voltage also known as a Volt Watt curve The 4 points of the default curve where you can set the of Vnom values and related of Pmax can be modified using the internal Webserver When enabled the curve will be set in the inverter Frequency Watt function Frequency Control P f In this mode the inverter limits the active power as a function of t...

Reviews: