Festo PDAD Series Application Note Download Page 16

Layout of purge air regulation for reducing air consumption 

 

Application note 

 Energy management function at adsorption dryer PDAD 

 1.10                                                      Page 16 of 17 

4.

 

Connect external switching logic (NC contact of the manual switch, the pressure switch or on the relay) to 
terminals 1 and 2 in the plug insert of the DIN plug. Make sure that the wires and cables are correctly 
stripped and that good insulation is assured through the cable gland! 
 

5.

 

Measure continuity between the two wires if possible with a measuring instrument, in order to ensure 
that the switch is current-free in the closed position. Check for correct switching function if possible as 
well. A 5 V DC signal is read out from terminal 1 during operation which is fed to terminal 2 via the NC 
contact, by means of the EM function can be activated or deactivated. 

 

6.

 

Carefully pull the cable back through the sleeve until the insert snaps back into the housing of the DIN 
plug. Observe the direction in which the cable throughfeed must point. 

 

7.

 

Insert the DIN plug back into the energy management connection at the dryer and screw it tight, making 
sure that the sealing ring is correctly seated. The protective conductor terminal is somewhat wider than 
terminals 1 and 2. Make sure that the socket plug is correctly aligned. 

 

The selected cable to the switching logic … 

 

  must have at least 2 conductors. Additional conductors may be useful in the event that a conductor is 

broken. Conductors can be changed without having to lay a new cable.  

  may not have a wire cross-section of any greater than 1.5 sq. mm (recommended) in order to freely fit 

into the DIN plug insert.  

• 

  should have an outside diameter of no more than 6 

mm. Larger diameters don’t fit well into the cable 

gland of the DIN plug for the energy management function.  

  should demonstrate insulation characteristics which are suitable for the conditions of use. 

 

8.

 

Restart the dryer in accordance with the operating instructions. 
 

9.

 

Test the energy management function (switch manually or by adjusting the switching points) without yet 
discharging compressed air! Recommendation: shut-off device (2/2 function) downstream from the PDAD 
 

10.

 

If  reliable  functioning  is  assured,  slowly  open  the  shut-off  device  and  release  compressed  air  to  the 
application. 
 

11.

 

Renewed testing and long-term observation of the EM function, as well as adjustment of the switching 
points during normal operation. Pressure, as well as the pressure dew point, should not drop to below 
the minimum requirement!  
 
 
 
 

Supplementary notes for the operating instructions: 

The use of an ideal air reservoir downstream from the PDAD smooths pulsation caused by discharging air. 
 
The pressure dew point to be achieved is based on the flowing quantity of air. Consequently, a higher pressure 
dew point is achieved with a lower flow velocity. On the other hand, a higher or excessively high flow rate may 
result in a reduced pressure dew point. For this reason, the table values listed in the catalogue should always be 
complied with. The dischargeable flow rate is listed there depending on the size of the PDAD, operating pressure, 
the available amount of air and the required pressure dew point.  
 

 

Summary of Contents for PDAD Series

Page 1: ...e Energy management function at adsorption dryer PDAD Application note for use of the energy management function at adsorption dryer PDAD Explanation use and layout of purge air regulation for reducin...

Page 2: ...used for the implementation of safety relevant functions for the protection of personnel and machinery No liability is accepted for claims for damages arising from failure or malfunctioning Otherwise...

Page 3: ...easonably foreseeable misuse 7 2 4 Environment used in 7 2 5 User groups 7 2 Layout of purge air regulation for reducing air consumption 8 3 1 Nature of the task 8 2 2 Use of a manual switch for purge...

Page 4: ...onents 1 2 Documentation This application note is intended to supplement existing documents to include the energy management function Catalogue documentation https www festo com cat en gb_gb data doc_...

Page 5: ...at the interface matter between two phases Adsorption dryers draw the moisture out of the compressed air through the use of a drying agent While adsorption takes place in the first container regenera...

Page 6: ...g instructions The software is neither provided by Festo nor is it available because the device can be damaged in the event of incorrect settings The PDAD is also equipped with an alarm connection whi...

Page 7: ...idges may never be entirely saturated In any case checking must be conducted for continuously flawless functioning because the dryer might otherwise fail or errors might occur within the process or th...

Page 8: ...sure drop although no air consumption is required for the application Compressor start up results in noise in some cases disagreeably at night The temperature in the room might also rise so that appli...

Page 9: ...y important to understand that the purge function can only be shut down at times when little or no air is required If this function is shut down at any other time the drying agent cartridges may be pe...

Page 10: ...portant to understand that the purge function can only be shut down at times when little or no air is required If this function is shut down at any other time the drying agent cartridges may be perman...

Page 11: ...wn until the pressure switch is once again released in this example at an overpressure of 6 2 bar or 90 psi The point at which the switch is released can be adjusted in accordance with the system If i...

Page 12: ...yer PDAD 1 10 Page 12 of 17 Figure 4 Use of a simple pressure switch for purge regulation Dryer regulator Pin 1 reads out 5 V DC signal Pressure switch installed in the field Signal output Return sign...

Page 13: ...s example at an overpressure of 6 2 bar or 90 psi The point at which the switch is released can be adjusted in accordance with the system It s very important to understand that the purge function can...

Page 14: ...tting i e purge air is also active at times when little or no purge air is required There s a plug inserted into the socket for the energy management function EM to this end with pre set jumper see fi...

Page 15: ...lay contact is opened purge air is deactivated The dryer should be removed from service before conversion or integration In order to remove the device from service disconnect it from supply power and...

Page 16: ...lay a new cable may not have a wire cross section of any greater than 1 5 sq mm recommended in order to freely fit into the DIN plug insert should have an outside diameter of no more than 6 mm Larger...

Page 17: ...ections and testing before commissioning All cables must be secured in an appropriate manner The device must be removed from service before conducting any maintenance or repair work Operators and othe...

Reviews: