Ferroli GNI User Manual Download Page 8

Supplied By www.heating spares.co  Tel. 0161 620 6677

8

4.02 Hydraulic connections

Boiler must be connected to the system according to boiler back part indications and those provided at fig.
2. Pipe must be free of any kind of strain and security valves must be provided in both central heating system
and domestic hot water system location of such security valves be as close is possible to the boiler and
between the boiler and valve no obstructions or gate valves must be placed.
The boiler is not supplied with expansion tank it has to be provided during the boiler installation. It is advised
that the pressure in the hydraulic system has to be between 0,5 and 1 bar measured in cold water condition.

4.03 Connection to the chimney

It is recommended to connect the boiler to a good working chimney built according to the regulations. The
connection between boiler and chimney must be done by using suitable material proof against high
temperature and corrosion. Where flue sections have to be connected it is advised pay attention to avoid
leaking and provided good insulation through all the flue length to avoid condensing problem.

5. Testing

5.01 Before the first light of the boiler

Before the first light of the boiler follow these check list:

a) check the system is filled with water at the right pressure;

b) check against any leakage of water fuel;

c) check that the correct electric power is supplied to the unit;

d) check size and perfect flue installation;

e) check against any type of flammable materials where the boiler is installed;

f) check the burner has the right heat input according to the boiler size;

g) control that the water valves are open.

5.02 First lighting

After the boiler preliminaries checking , the appliance can be lights in the following way;

1) Open the fuel gate valve.

2) Set the regulating thermostat at the required temperature level.

3) Give electric power to the boiler and switch on the main switch 4 (fig. 1) on the boiler control panel.

After above operations the burner will start to run and the boiler will begin to work.

5.03 After the first lighting

After the first lighting it is advisable check:
burner works properly, this checking must be done by appropriate instruments.
Thermostats operate correctly.
Water flows through the system.
Smoke gases evacuate through the flue duct.

Summary of Contents for GNI

Page 1: ...Supplied By www heating spares co Tel 0161 620 6677 GN1 CAST IRON HIGH EFFICIENCY SECTIONAL BOILER FOR GAS OIL FUELS...

Page 2: ...Supplied By www heating spares co Tel 0161 620 6677 2...

Page 3: ...ed By www heating spares co Tel 0161 620 6677 3 Index 1 Technical informations 2 Dimensions and technical data 3 Packing and shipping details 4 Installation 5 Testing 6 Service 7 Boiler components 8 O...

Page 4: ...meter 3 Security thermostat manual resetting 4 Main switch 5 Control thermostat 1 02 Control and securities devices operation Regulating thermostat manual resetting 3 fig 1 It operates when the boiler...

Page 5: ...2 39 3 49 1 59 1 68 8 78 6 Heat and D H W net gas oil Min 16 4 16 4 35 4 44 2 53 2 62 0 70 8 Heat and D H W output Min 15 0 15 0 32 5 40 5 48 8 57 0 65 0 N element 2 3 4 5 6 7 8 Water capacity dm 3 11...

Page 6: ...p fig 3 Pressure drops according to the boiler size are specified on the following diagram and refer to temperature difference between flow and return comprises between 10 and 20 C Fig 3 3 Packing and...

Page 7: ...ure that the law is coplied with Manufacturers instructions must NOT be taken in any way as over riding statutory obligations special care must be paid to conform with law and regulation concerning bu...

Page 8: ...d provided good insulation through all the flue length to avoid condensing problem 5 Testing 5 01 Before the first light of the boiler Before the first light of the boiler follow these check list a ch...

Page 9: ...liquid in the system or to drain it completely 6 Service The after sale service must be carried out only Qualified Plumbers It is advise to service the boiler at least once a year before the winter se...

Page 10: ...36401210 BOILER THERMOSTAT 26 36901140 NO RETURN VALVE 27 37025600 FRONT PANEL 28 37025610 RIGHT PANEL FOR GN1 02 28 37025620 RIGHT PANEL FOR GN1 03 28 37025630 RIGHT PANEL FOR GN1 04 28 37025640 RIGH...

Page 11: ...Supplied By www heating spares co Tel 0161 620 6677 11...

Page 12: ...heating spares co Tel 0161 620 6677 cod 3540590 0 03 97 ALL SPECIFICATIONS SUBJECT TO CHANGE Stockton Close Minworth Industrial Park Minworth Sutton Coldfield West Midlands B76 8DH Tel 0121 3523500 F...