MAINTENANCE MANUAL – ELECTRIC ROTARY DRYER
FERREX ENGINEERING LTD.
Page 12
Ref. #2278
BAGHOUSE SECONDARY HEATER PANEL
1. Install the Panel agecent to the main dryer electrical panel.
2. Follow Drawing 2270-300-E-002 to run the main 400 Amp 480V 3phase 60Hz power
supply to the panel.
3. Wire the two 75kw heaters to the main panel as shown on drawing 2270-300-E-002
4. Wire the clean side fan, rotary valve for the baghouse, and secondary heater fan as per
drawing 2270-300-E-002.
5. Wire baghouse cleaning valves, and baghouse enclosure heater 120V circuits as per
drawing 2270-300-E-310 and 2270-300-E-341.