4
STEP-BY-STEP
GUIDE
0800 002 725
|
fentec.co.nz
Bottom Rail
Top Rail
Check Installation
Palings
STEP 3 -
INSTALLING RAILS | INSTALLING PALINGS
3.1
3.2
3. 3
3.4
-
Slide the first paling into the bottom rail with the
groove in end of paling to the bottom.
-
Ensure a 15mm gap is between the edge of paling
and the inside face of the post and push down firmly
into the bottom rail. A rubber mallet can be used if
required.
-
Continue to insert all palings, ensuring the tongue
and groove joint is in place correctly.
-
Once all palings are installed it is time to fit your
top rail.
-
Place over the top of the palings, and tap down into
the C post. Once in place, fix both sides of the rail to
the C post using the tech screws provided. The top of
the rail should be 15mm from the top of the post.
-
Slide the first paling into the bottom rail with the
tongue in edge of paling to the top.
-
Ensure a 15mm gap is between the end of paling
and the inside face of the post and push down firmly
into the bottom rail. A rubber mallet can be used if
required.
-
Continue to insert all palings, ensuring the tongue
and groove joints are in place correctly.
-
Once all palings are installed it is time to fit your
top rail.
NOTE:
when building a 1800h horizontal fence the
7th (top) paling is to be cut down in width to suit
total height needed.
For
EasyWall Vertical
For
EasyWall Horizontal
Bottom rail
between
C posts
C Posts
Appr
ox. 50mm
-
Insert bottom rail between posts.
-
Adjust bottom rail to correct height - it is important to
maintain a minimum gap of 50mm between bottom of
rail and ground.
-
Screw fix the bottom rail at this stage.
NOTE:
EasyWall Vertical fence system is supplied with
a Rail Support and this is to be inserted inside the
bottom rail prior to it being installed.
Top rail