Hardware Setup
The list below outlines the necessary steps for getting the LPC3180 and optional GUI
board up and running. Images are provided where necessary as visual aides to the setup
process.
1.
Place LPC3180 and GUI boards on a flat surface.
2.
OPTIONAL: Connect GUI board to LPC3180 board by lining up connectors J12
and J13 of the LPC3180 board with connectors J1 and J2 of the GUI board,
respectively. Push the boards together until a complete connection is made (see
Figure 1).
3.
Connect Condor Power supply from wall outlet to P3 on the LPC3180 board (see
Figure 3).
4.
Setup serial connection and HyperTerminal as described in section 2.6 (see Figure
2).
5.
Toggle switch SW1 to provide power to the board(s) (see Figure 3). Text should
be immediately visible in the HyperTerminal window and on the LCD panel (if
connected).
6.
If JTAG is immediately required, please consult section 4.1 on installing JLink
Commander and 6.0 on connecting JTAG for downloading software.
Figure 1: GUI Board Connection
Figure 2: Serial Connection
Figure 3: Power Switch
Summary of Contents for LPC3180
Page 32: ...FDI NXP LPC3180 Demo User s Manual FDI Rev 2 Page 32 10 1 2007...
Page 33: ......