FarmTek 2420SVSPC Manual Download Page 8

CANOPIES

8

Revision date: 10.13.15

Frame Assembly Procedure

 

Arrange the roof pipes on the ground adjacent to the  

correct couplers needed to assemble the roof.
1.  Connect the ridge pipes (58" purlin section) using a  

3-way coupler on the end rafter and 4-way couplers  

for the interior the sections. The assembled length 

should match the shelter length. 

 

 

NOTE:

 The last ridge pipe will finish with a 3-way 

coupler. Verify that the correct pipe is used.

2.  Attach the rafter pipes as shown in the illustration. Each 

rafter is assembled using one (1) 58" plain pipe and 

one (1) 99" swaged pipe with Tek screw used to secure 

the joint for each side of the rafter. 

IMPORTANT

: Slide a band clamp (#QH1402) onto 

each 58” rafter pipe

 before securing to the other rafter 

pipe and coupler.

LAY OUT THE BUILDING SITE

After the site is prepared, identify the location of the shelter 

corners to help square the frame after it is assembled.

Taking these steps 

before

 assembling the shelter saves 

time and ensures that the structure is positioned as 

desired. The following procedure is a suggested method.

Its use depends on the size of the shelter, shelter 

application, the footings, and the method used to anchor 

the shelter.

SQUARE THE SITE

1.  Identify a corner where a building rafter will be  

positioned, drive in a stake, and string a line the exact  

width of the building and stake in place. 

2. 

Sting a line at least as long as the building from the first 

 

stake at 90°. 

 

NOTE:

 A transit can be used to ensure an accurate 90°  

angle, or the 3-4-5 rule can be used. Refer to diagram.  

Using multiples of 3-4-5 such as 6-8-10 or 12-16-20  

helps to maintain an accurate 90° angle.

3.  After squaring the position of the building and placing  

a stake at all corners, string a line between the stakes  

to mark the base of the building.

3.  Connect the 3-way couplers to form the end rafters 

of the roof assembly and connect the 4-way cross 

couplers to construct the inside rafters.  

 

NOTE:

 Position the eye bolts of the couplers to the 

inside of the frame and tighten.

FRAME ASSEMBLY
NOTE:

 With longer shelters, assembly may require shelter 

to be assembled in short sections and then lifted and 

connected for completion. 

Gather the parts:
•  Pipes 1.66" x 99" swaged (166S099) 
•  Pipes 1.66" x 58" plain (166P058)
•  Pipes 1.66" x 77" plain (166P077)
•  Horizontal strut (#QH1308) & band clamp (#QH1402)
•  3-way couplers & 4-way couplers 
•  Tek screws (#FA4482B)

4-Way Coupler

3-Way 

Coupler

End 

Rafter

Inside 

Rafter

Inside 

Rafter

58"

Ridge 

Pipe

58"

Band 

Clamp

99"

Summary of Contents for 2420SVSPC

Page 1: ...s Reserved Reproduction is prohibited without permission Sunblocker Shade House 24 Wide Photo may show a different but similar model STK DIMENSIONS 2420SVSPC 24 W x 20 L 2430SVSPC 24 W x 30 L 2440SVSPC 24 W x 40 L 2450SVSPC 24 W x 50 L 2460SVSPC 24 W x 60 L ...

Page 2: ... and may cause serious injury and damage LOCATION Choosing the proper location is an important step before you begin to assemble the structure The following suggestions and precautions will help you determine whether your selected location is the best location Never erect the structure under power lines Identify whether underground cables and pipes are present before preparing the site or anchorin...

Page 3: ... assembly read through the following definitions before you begin to assemble your shelter Conduit An assembly of pipes used to secure the main cover and end panels if equipped Purlins and some strut assemblies also consist of connected pipes to form a conduit Each pipe joint of a conduit assembly is secured with a self tapping Tek screw Coupler or Fitting A part of the frame assembly where legs p...

Page 4: ...ify that all parts listed on the Bill of Materials Spec Sheets are present If anything is missing or you have questions consult the Pictorial Parts Guide and all shelter diagrams for clarification or contact Customer Service at 1 800 245 9881 NOTE At this time you do not need to open the plastic bags containing smaller parts such as fasteners or washers ALTERNATIVE ASSEMBLY INFORMATION These instr...

Page 5: ...p you identify the different parts and show you how they are used Some parts are not shown CC4595 Tie Down 8 Snugger Ball 102193 3 Way Coupler 102194 4 Way Coupler FA4482B Tek screw 100441 Nut Setter QH1402 Band Clamp Swaged Plain Swaged and Plain Rafter Sections QH1308 7 Strut ...

Page 6: ...ury and damage to the shelter fasten and tighten a Tek screw at each pipe and coupler joint To prevent cover damage install the Tek screw so that it does not touch the main cover or any optional side or end panels once these are installed 4 Way Coupler no lock bolt 4 Way Coupler includes lock bolt ADDITIONAL PARTS IDENTIFICATION NOTES In some instances there can be differences between the parts th...

Page 7: ...For details of each assembly procedure consult the Frame Overview and the individual sections of these instructions See illustration below to identify main parts of shelter 1 Layout the site and identify the required parts for each assembly procedure 2 Assemble and anchor the frame 3 Prepare and install the main cover NOTE Actual frame may differ from frame shown ...

Page 8: ...cation the footings and the method used to anchor the shelter SQUARE THE SITE 1 Identify a corner where a building rafter will be positioned drive in a stake and string a line the exact width of the building and stake in place 2 Sting a line at least as long as the building from the first stake at 90 NOTE A transit can be used to ensure an accurate 90 angle or the 3 4 5 rule can be used Refer to d...

Page 9: ...er assemblies FRAME TOP VIEW 3 Examine the frame and remove any sharp edges from the frame or reposition screws if equipped so they do not come in contact with the roof cover 4 After the frame is squared read or reread the MUST READ document and anchor the shelter FRAME ASSEMBLY CONTINUED 4 Add horizontal struts QH1308 between rafter pipes at each rafter Secure at each end using a band clamp as sh...

Page 10: ...d frame See the above insert Use one snugger ball for each grommet 3 Once the main cover is installed unfold the optional side covers additional purchase required along the frame and attach them to the main roof frame using the snugger balls The dashed line in the diagram below shows where to attach the side cover 4 Read the Care and Maintenance section that follows WARNING To prevent property dam...

Page 11: ... that will not damage the cover when removing debris Remove snow to prevent excess accumulation Use tools that will not damage the cover when removing snow Check the contents of the shelter to verify that nothing is touching the cover that could cause damage Check the anchoring system to ensure that all components are tight and in good repair If the shelter is moved inspect all parts and connectio...

Page 12: ... 12 Revision date 10 13 15 QUICK START GUIDE 24 Wide Sunblocker Shade House NOTE Actual frame may differ from frame shown Width 22 10 11 16 Height 13 1 15 16 6 5 Endwall Height Grid Represents 12 Squares FRONT ...

Page 13: ...d Rafters 102193 Mid Rafters 102194 End Rafters 102193 Mid Rafters 102194 End Rafters 102193 Mid Rafters 102194 166S099 1 66 pipe 99 166P058 1 66 pipe 58 166P077 1 66 pipe 77 166P077 1 66 pipe 77 166P058 1 66 pipe 58 166S099 1 66 pipe 99 QH1308 7 Strut ...

Page 14: ...CANOPIES 14 Revision date 10 13 15 SIDE PROFILE 2420SVSPC 166P058 1 66 pipe 58 Rafter Spacing 5 0 20 0 Length ...

Page 15: ...15 CANOPIES Revision date 10 13 15 SIDE PROFILE 2430SVSPC 166P058 1 66 pipe 58 30 0 Length 5 0 Rafter Spacing ...

Page 16: ...CANOPIES 16 Revision date 10 13 15 SIDE PROFILE 2440SVSPC 166P058 1 66 pipe 58 40 0 Length 5 0 Rafter Spacing ...

Page 17: ...17 CANOPIES Revision date 10 13 15 SIDE PROFILE 2450SVSPC 166P058 1 66 pipe 58 50 0 Length 5 0 Rafter Spacing ...

Page 18: ...CANOPIES 18 Revision date 10 13 15 SIDE PROFILE 2460SVSPC 166P058 1 66 pipe 58 60 0 Length 5 0 Rafter Spacing ...

Page 19: ...n View 2 Mid Rafter Purlin Connection View 3 Rafter Chord Connection 102194 Purlin Rafter QH1402 Band Clamp Rafter QH1308 7 Strut View 1 End Rafter Purlin Connection End Rafter Purlin Connection View 1 Rafter Chord Connection View 3 Mid Rafter Purlin Connection View 2 ...