ESTIMATING & ORDERING A ROOF
Step 3
Refer to the Home Legend for trim placement. From this diagram, you can determine the names and placement
of the trim needed. All trim is produced in 10’ sections only. Remember to allow 6” of overlap on all trims. Use
the estimating section to determine trim quantities.
5V CRIMP - Estimating Guide
Accessories
Determine the total lineal feet of each condition listed below and then fill that number in on each line. Use the
equations on previous pages to calculate the number of pieces for each item and circle the flashing design
required.
Eave __________
Ridge __________
Gable __________
Sidewall __________
Endwall __________
Hip ______________
Valley ____________
Transition _________
Gambrel __________
Skylight/Chimney width =
_________
5V CRIMP
Estimating Guide
Insert the total lineal feet of each condition into the equations below to determine required trim.
Eave: ______ ft. ÷ 9.5’ = _______pcs. - CE-1 EAVE
Ridge: ______ft. ÷ 9.5’ = _______pcs. - RR-1 RIDGE CAP
Gable: ______ft. ÷ 9.5’ = _______pcs. - WG-1 GABLE TRIM
Sidewall and Endwall: (______ft. si _______ft. endwall) ÷ 9.5’ = ________pcs. - ASW-1 TRIM
Hip: _______ft. ÷ 9.5’ = _______pcs. - RR-1 RIDGE
Valley: _______ft. ÷ 9.5’ = ________pcs. - RV-2 W-VALLEY
Slope Transition: _______ft. ÷ 9.5’ = ________pcs. - AT-1 TRANSITION
Specify both pitches ____:12 and ____:12
Gambrel: ______ft. ÷ 9.5’ = _______pcs. - AT-2 GAMBREL
Specify both pitches ____:12 and ____:12
Fastener Calculations:
Panel Screws - Based on 18” o/c fastening. Approximately 2 screws per lineal ft of panels, #14 x 1 Mill Point or
#14 x 1½ Mill Point
Panel Lin. Ft. _______ x 2 =
______ #14 x 1 Mill Point
______ #14 x 1½ Mill Point
5V CRIMP