3
5X5M CORRECT ROOF PLACEMENT
Recommended procedure below. For safety reasons it is recommended that 2 persons set-up any Marquee.
1. Open frame 75% of full extension and fit
the roof to the frame.
2. Connect the velcro on roof corners to the
velcro on the corners of the marquee legs.
3. Fit the peak of the roof to the centre poles
of the marquee and tighten the toggle.
5X5M PACK DOWN INSTRUCTIONS
Recommended procedure below. For safety reasons it is recommended that 2 persons pack down any marquee. Be sure to remove any items used
to secure the marquee to ground before packing it up.
1. Release lower leg pins and fully retract left
middle leg followed by corner legs. Repeat
for right side legs.
5. Walk marquee in by grasping ‘LIFT HERE‘
section. At a quarter of the way, undo the
velcro straps to remove roof for transport.
2. Unclip roof straps from truss bars.
3. Pull the lower pin to release the centre pole,
followed by upper pin to retract upper centre.
pole.
4. Release all roof corner pins.
6. Fit the protective cover to frame and store
roof in a protective bag.