EternaCell BLSe 12-100 Operating, Installation, Maintenance Instructions Download Page 8

Place the cells on the rack and make sure that the spacing allows the accommodation of the supplied inter-cell 
connectors (approximately 0.4”).  Most batteries have cells connected in a simple series arrangement, so the cells 
should be arranged to preserve the polarity sequence.  

I.e.

, (+)…(-)…(+)…(-)…etc. 

NEVER LIFT CELLS BY THE TERMINAL POSTS. ALWAYS USE APPROPRIATE DEVICES  (SUCH AS 
LIFTING STRAPS AND SUITABLE MECHANICAL EQUIPMENT) TO PREVENT INJURY TO 
PERSONNEL OR DAMAGE TO THE CELLS. 

For batteries to be installed on multiple tiers, start by placing the cells on the lower tier on either side of the frame 
where the stand sections meet.  Any unused stand space should be on the upper tier. 

For batteries on stepped racks, leave any unused space on the back (top) step. 

Where multiple racks are arranged end-to-end, adjust the position of the adjacent end cells to accommodate the 
flexible inter-rack connectors supplied. 

Take particular care to preserve the positive to negative sequence when using flexible inter-tier, inter-step or inter-
rack connectors between rows of cells.  Leave the main positive and negative terminals of the battery free for 
connection to the charger and loads. 

Check cell alignment. 

Prepare the inter-cell connectors by lightly abrading the contact surfaces with a fine grit abrasive paper.  Do not 
use a wire brush and be especially careful not to break through the lead plating. 

Apply a light coating of no-oxide grease to the contact-making areas of each connector.  This is best done by 
carefully melting the grease and dipping connector ends (it is unnecessary to coat the central part of the 
connector). 

Fit the inter-cell and inter-tier connectors using the bolts, nuts and washers supplied.  Before assembly, lightly 
smear no-oxide grease on the surfaces of all hardware. 

Use insulated wrenches or sockets to tighten the parts firmly together (see the table below for torque settings). 

BLSe block batteries 6V - 12V 

70 inch pounds (8 Nm) 

LSe cells 2V 

90 inch pounds (10 Nm) 

 

Pay special attention to avoid short-circuiting the cells with any of the battery hardware. 

Check tightness and cleanliness. 

Make sure that all vent caps are closed. 

Connect the positive terminal of the battery to the positive terminal of the charger and the battery negative to the 
charger negative. 

Number the cells with the numbers supplied with the battery.  It is common practice to number the cells beginning 
with #1 at the positive end of the battery and following the sequence of electrical connection of the cells to the 
negative end of the battery. 

8.0 Charging 

8.1  Initial Charge of Dry Cells 

 

An initial or freshening charge must be given to all batteries before being put into service.  This is 
most important for cells supplied in dry charged conditions and filled on site. 

Summary of Contents for BLSe 12-100

Page 1: ...LSe and BLSe range Operating Installation Maintenance Instructions...

Page 2: ......

Page 3: ...6 0 Battery Room 3 7 0 Installation 3 8 0 Charging 4 8 1 Initial Charge of Dry Cells 4 8 2 Filled and Charged Cells Freshening Charge 5 8 3 Charging in Service 6 9 0 Specific Gravity 7 10 0 Maintenanc...

Page 4: ......

Page 5: ...equipment such as rubber gloves and goggles If acid is spilled on the skin wash immediately with copious amounts of clean water then cover with dry gauze If acid comes into contact with the eyes flus...

Page 6: ...with adequate ventilation to disperse the gases formed while charging If continuous charging is not possible the battery should be given a freshening charge at least every 60 days until permanently i...

Page 7: ...n working within the range of 68 F 20 C to 77 F 25 C but will function at temperatures between 0 F 18 C and 125 F 52 C High temperatures increase the performance but reduce battery life while low temp...

Page 8: ...it abrasive paper Do not use a wire brush and be especially careful not to break through the lead plating Apply a light coating of no oxide grease to the contact making areas of each connector This is...

Page 9: ...ing interval to every hour and continue charging until specific gravity and voltage remain constant for two hours and each cell has reached a minimum of 2 6V If the charger does not allow the cells to...

Page 10: ...harge or that the cells should be topped up For comparison of electrolyte specific gravity vs temperature please refer to section 9 0 8 3 2 Equalize Charge Chargers usually have two adjustable voltage...

Page 11: ...quired safety precautions should perform battery maintenance For regular monitoring of the battery condition a pilot cell should be selected The pilot cell should be near the middle of the battery str...

Page 12: ...of Eternacell B LSe batteries is minimized when floating at 2 23V cell at 77 F 25 C Consumption increases at higher temperatures and or higher float voltages Never allow the electrolyte level to fall...

Page 13: ...2 8 3 28 6 132 8 178 2 4 39 4 LSe 1100 2 1096 10 8 8 3 28 6 145 7 201 8 5 42 4 LSe 1200 2 1200 10 8 8 3 28 6 155 2 210 5 5 34 4 LSe 1300 2 1272 10 8 8 3 28 6 164 7 218 8 5 23 4 LSe 1400 2 1376 10 8 8...