into the sleeve to remove the rotor from the shaft of the generator(see fig.8). After repairing 
the imbalance, reassemble. Torque should less than 0.02N.m.   

 

6. Maintenance of the wind generator 

The  products  are  divided  into  two  types:  common  product  and  high  quality  product  (no 
maintenance). The common product needs the following maintenance regularly: 
6.1. Check, clean and lubricate all rotating parts once per year. 
6.2 Before rainy season or winter depending on climate, clean outside and paint anti-rust grease 
on all fixed connecting cables and tower parts once a year.   
6.3 Lubricate and maintain bearing of generator once per operating year. 
6.4. Clean, remove rust and paint all exposed parts once every two years.   
The maintenance of high quality product (AAA) 
a.  Exposed  parts  are  made  of  stainless  steel  and    have  been  treated  by  special    long  life 
rust-protection    treatment, so the outside of those parts do not need maintenance. 
b. The generator has high grade bearings and high grade lithium grease. The bearings need to 
be  checked  after  operating  for  5  years.  If  it  is  necessary,  add  some  lithium  grease  to  the 
bearings. 
6.5  Inspect  ground  rod  connection  to  the  turbine  mast  to  ensure  the  wire  is  still  in  place  and 
secure. 
 

7. Troubleshooting 

The  wind  generator is  designed  and  manufactured  to  be  trouble-free  and  low-maintenance.  If 
the  installation  and  operation  are  correct,  failures  will  not  appear  under  normal  conditions.  In 
case of failure, please consult following table.     
 

Trouble 

Reason 

Solution 

Wind 

generator 

vibrating strongly 

1. Steel cable guy line is loose. 
2. Hub blade bolts are loose. 

3.  Blade  is  defective  caused  by 

outside force. 

4. Ices over on the surface of blades, 

causes imbalance. 

1.  Tighten the appropriate steel guy line. 
2.  Tighten the loose parts. 

3.  Replace with a new blade and adjust the 

rotor balance if required. 

4.  Eliminate    the  attached  ice.  Wax  the 

blades to prevent future ice attachment. 

Direction  regulating 
is ineffective 

1.  There  is  too  much  greasy  dirt  in 

the rotating body. 

2.  Rotating  part  is  deformed  by 

outside force. 

3.  The 

clearance 

between 

the 

vertical  shaft  and  sleeve  is  too 
small, or there is no movable axial 
clearance. 

1.  Clear away the dirt and grease. Replace 

with fresh grease. 

2.  Recover and correct the deformation. 

unusual noise 

1.  Fixed parts are loose 
2.  Generator bearing is damaged 

3.  Wind  rotor  is  rubbing  with  other 

parts. 

 

1.  Put the wind turbine down on the ground, 

check  every  fixed  part,  and  take 
appropriate measures. 

2.  Replace the damaged bearing. 

3.  Checking and eliminate the trouble. 

 

The  rotating  speed 
of  the  wind  rotor  is 
obviously reduced   

1.  Blade pitch control is ineffective. 
2.  Stator  winding  is  short 

–circuited 

or output circuit is shorted. 

 

1.  Check  and  eliminate  the  trouble,  then 

lubricate. 

2.  Find  out  short  circuit  position,  split  the 

lines and isolate them.. 

Summary of Contents for 2KW WIND TURBINE

Page 1: ...2KW WIND TURBINE Operation Manual GRADE AAA Please read carefully before using EST energy saving technology ESPECIALLY DESIGNED FOR EST LEBANON ...

Page 2: ...DC48v Generator style Three phase permanent magnet Charging method Constant voltage current saving Speed regulation method Yawing Electromagnetic brake Stop method Manual brake Tower height m 6 Weight kg not including batteries or inverter Main unit 95 Total 155 3 Preparation 3 1 Prepare batteries according to manufacturers specifications 3 2 Unpack and check the turbine parts and verify all parts...

Page 3: ...y 20cm Put the loop for guy wire through the loop welded to the tower section Close the loop with two wire clamps Repeat for each of the remaining cables 4 4 Put the heart ringer for steel wire across the o loop of turnbuckle and then rip the steel wire into the heart ringer Bend for a loop no less than 30cm long fasten with wire clamps Hook the turnbuckles of A B and D pits to the chain of anchor...

Page 4: ...e steel wires to make the mast in its vertical position Strain the steel wire until it can rebound lightly when gives a transverse force 4 14 Check the wire block screw buckle and all connecting point Make sure it is safe Then wrap and blocked them with galvanized wire Put anti corrosive grease on wire block screw buckle and all links where necessary 4 15 Connect the batteries in series to be a gr...

Page 5: ...ent damage 5 2 6 The power supply line of the wind generator should be run independently It can not be mixed used with other power supply lines DC power supply is safer and more efficient for lights For home electric appliances an AC power supply line from an inverter should be used It is suggested that the connector of a refrigerator should be inserted in a special plug with a timer to control it...

Page 6: ...e free and low maintenance If the installation and operation are correct failures will not appear under normal conditions In case of failure please consult following table Trouble Reason Solution Wind generator vibrating strongly 1 Steel cable guy line is loose 2 Hub blade bolts are loose 3 Blade is defective caused by outside force 4 Ices over on the surface of blades causes imbalance 1 Tighten t...

Page 7: ...e wires so as to reduce circuit electricity loss There is no output electric current in AC circuit of the Generator 1 There is a broken wire in the AC lines of the generator 2 There are circuit break in output line 3 Stator winding is burnt circuit is open Find out the reason and connect the wires 1 Find out the broken point then connect the wires 2 Disassemble then repair the damaged coil AC outp...

Page 8: ...Fig1 2KW WIND TURBINE SYSTEM AAA ...

Page 9: ......

Page 10: ......

Page 11: ......

Page 12: ...HY 2KW WIND TURBINE WIRING DIAGRAM ...

Reviews: