IQ System Controller 2 Quick Install Guide
CONDUIT LOCATION
MAIN
BACK UP
DER
Bottom
Left wall
Right wall
Section C
Wiring
Drill conduits
Drill conduit entry holes as needed, and install conduit grounding
lugs for each opening. Be sure to reseal unused conduit entry holes
with sealing plugs.
NOTE: Main supply conductors may enter the IQ System Controller
2 from the bottom or from the bottom-left side. Backup load
conductors may enter the IQ System Controller 2 from the bottom
or bottom-right side. IQ Batery, IQ Combiner and generator
conductors may enter from the bottom, bottom-left or bottom-right
sides.
Size the conductors (Line, Neutral and Ground) depending on the
breaker or fuse, proper ampacity, and voltage rise requirements
according to local codes.
Refer to the conductor rating table on the door of the IQ System
Controller 2.