7.0 SYSTEM
INSTALLATION
7.1 System
Layout
Lay out the battery system before installation. Consult Section 5.0 for installation considerations.
1.
Locate the system position in the area designated as determined in Section 5.0.
2.
Mark the floor with system outline dimensions.
3.
The floor must be level. Shimming up to 1/4 inch (6 mm) may be required to have the
Battery System fully level.
4.
Batteries should be kept in the original shipping containers until installed. However, if you
must remove the batteries before installation, see the procedures in Section 6.3,
“Cell/Battery Handling.”
NOTE:
The floor must be capable of supporting the weight of the Battery.