Enerpac ATM-2 Instruction Sheet Download Page 3

3

4.0  OPERATING INSTRUCTIONS 

1. Determine the maximum point of misalignment.

2. Guide the lift hook of the tool into the bolt hole 

at the maximum point of misalignment. The drop 

leg should be released and lowered onto the pipe 

while the hook is held level in the bolt hole. It then 

must be secured in position by tightening the 

thumb screw. See Fig. 2.

PARALLEL

Fig. 2  Assembly of Tool on Flange

LIFT 

HOOK

THUMB 

SCREW

DROP 

LEG

3. Rotate the screw handle clockwise until the driven 

wedge makes contact with the opposite flange. 

Thread the strap through the aperture on the base 

of the drop leg, feed the end of the strap through 

the buckle, and close the clasp. See Fig. 3.

Fig. 3  Strap Installation

STRAP 

APERTURE

STRAP

4. Rotate the screw handle clockwise until alignment 

is achieved. See Fig. 4.

WARNING:

 Do not exceed 45 lbf. [200 N] 

hand pressure on the screw handle. 

Handle may break if greater force is 

exerted. Never use tools to turn the handle.

5. When alignment is completed, the flange bolts 

may be inserted and tightened. After replacing all 

of the bolts in all open bolt holes (except for the 

bolt hole in which the tool lift hook is inserted), 

remove the tool by reversing steps 1 through 4.

Fig. 4  Alignment

Maximum Recommended handle-

force =  45 lbf. [200 N].
OPERATE HANDLE BY HAND 

ONLY - DO NOT USE TOOLS!

HAND 

CRANK

6. After removing the tool from the flange, install the 

last flange bolt in the remaining bolt hole.

5.0  EXAMINATION - MAINTENANCE

•  After finishing the job and before the tool is placed 

back into service, the completeness of the ATM-2 

tool must be established and items examined to 

ensure that they are serviceable.

•  Any missing or damaged items are to be replaced 

as soon as possible and prior to the tool being 

used again.

•  Grease all moving parts regularly with Mobilgrease 

XHP ™ 222 Special grease. Refer to Section 6.0.

•  Return all items to the carrying case when not in 

use.

6.0  INSPECTION AND LUBRICATION

(See Fig. 5 on next page)

STEP 1.  Place tool flat on work bench.

STEP 2.   Using a small, flat screwdriver, remove 

circlip. Then, remove five 4mm hex screws.

STEP 3.   Remove cover plate and remove any dirt 

or corrosion from moving parts.

STEP 4.   Inspect components for wear and damage. 

Replace as required. If no damage is 

present, then grease and reassemble 

parts by reversing steps 1 through 4.

Note:

 Use Mobilgrease XHP ™ 222 Special grease 

or an equivalent good quality high load bearing 

grease.

Summary of Contents for ATM-2

Page 1: ...ions 4 10 0 Range of Application Tables 5 7 11 0 Weights and Dimensions 8 For other languages go to www enerpac com Weitere Sprachen finden Sie unter www enerpac com Para otros idiomas visite www ener...

Page 2: ...mage such as excessive heat flame moving machine parts sharp edges and corrosive chemicals WARNING Immediately replace worn or damaged parts with genuine Enerpac parts Enerpac parts are designed to fi...

Page 3: ...hole in which the tool lift hook is inserted remove the tool by reversing steps 1 through 4 Fig 4 Alignment Maximum Recommended handle force 45 lbf 200 N OPERATE HANDLE BY HAND ONLY DO NOT USE TOOLS H...

Page 4: ...er that the 1 ton 10 kN capacity of the tool In this instance another method to align the joint should be adopted 8 0 STORAGE The ATM 2 should be stored in a cool dry place Machined surfaces are to be...

Page 5: ...7 8 9 10 12 13 14 15 16 17 18 19 20 TOOL ATM 2 ATM 4 ATM 9 CLASS S NPS 1 2 3 4 1 1 1 4 1 1 2 2 2 1 2 3 3 1 2 4 4 1 2 5 6 7 8 9 10 11 12 13 14 15 16 TOOL ATM 2 ATM 4 ATM 9 CLASS T NPS 1 2 3 4 1 1 1 4 1...

Page 6: ...0 42 44 46 48 TOOL ATM 4 ATM 9 CLASS 400 NPS 22 26 28 30 32 34 36 38 40 42 44 46 48 TOOL ATM 4 ATM 9 CLASS 600 NPS 22 26 28 30 32 34 36 38 40 42 44 46 48 TOOL ATM 4 ATM 9 CLASS 900 NPS 22 26 28 30 32...

Page 7: ...28 30 32 34 36 38 40 42 44 46 48 TOOL ATM 4 ATM 9 CLASS 2500 TOOL NPS 2 1 2 3 3 1 2 4 5 6 8 10 12 14 16 18 20 22 24 TOOL ATM 4 ATM 9 CLASS 5000 TOOL NPS 2 1 2 3 3 1 2 4 5 6 8 10 12 14 16 18 20 22 24...

Page 8: ...m 3 58 91 mm 1 99 50 mm 1 38 35 mm 1 46 37 mm 0 43 11 mm 3 23 82 mm 11 0 WEIGHTS AND DIMENSIONS 8 WEIGHTS Tool ratchet and strap 4 4 lbs 2 0 kg Box packing and instruction manual 0 9 lbs 0 4 kg DIMENS...

Page 9: ...Notes...

Page 10: ...Notes...

Page 11: ...Notes...

Page 12: ...www enerpac com...

Reviews: