Proline Promag 55 FOUNDATION Fieldbus
Installation
Hauser
11
3
Installation
3.1
Incoming acceptance, transport and storage
3.1.1
Incoming acceptance
On receipt of the goods, check the following points:
• Check the packaging and the contents for damage.
• Check the shipment, make sure nothing is missing and that the scope of supply matches your
order.
3.1.2
Transport
The following instructions apply to unpacking and to transporting the device to its final location:
• Transport the devices in the containers in which they are delivered.
• Do not remove the protection plates or caps on the process connections until you are ready to
install the device. This is particularly important in the case of sensors with PTFE linings.
Special notes on flanged devices
"
Caution!
• The wooden covers mounted on the flanges before the device leaves the factory protect the linings
on the flanges during storage and transportation. Do not remove these protection plates until
immediately before
the device is installed in the pipe.
• Do not lift flanged devices by the transmitter housing or, in the case of the remote version, by the
connection housing.
Transporting flanged devices (DN
≤
300) 12"
Use webbing slings slung round the two process connections. Do not use chains, as they could
damage the housing.
#
Warning!
Risk of injury if the measuring device slips. The center of gravity of the assembled measuring device
might be higher than the points around which the slings are slung.
At all times, therefore, make sure that the device does not unexpectedly turn around its axis or slip.
a0004294
Fig. 4:
Transporting sensors with DN
≤
300 (12")