background image

026-1700 Emerson is a trademark of Emerson Electric Co. ©2018 Emerson 

Climate Technologies Retail Solutions, Inc. All rights reserved. 

 

WM NextGen  

Case Controller 

Installation & Quick Start Guide  

 

 

 

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

        

        INSTALLATION GUIDE    

Carefully follow the steps below (REM and CAPX 
Installation as well as new stores) 

 

1. 

Mount and power up the new E2E panels. 

 

2. 

Connect the new Ethernet data cables to each E2E. 

 

3. 

Call Emerson Walmart Tech Support 24hrs prior to 
schedule E2E onboarding to the Walmart Network. 

 

a. 

Emerson Walmart Tech Support 479-845-3430

 

b. 

Have switch and port information available.

 

c. 

Ask Emerson Tech Support for Addressing 
worksheet 

4. 

Emerson Tech Support will load the programs onto the new 
E2E controllers. 

 

5. 

Contractor will install walk-in panels where needed for walk-
ins and old cases to be retrofitted.

 

a. 

See location of panels per the blueprints. 

 

6. 

New cases will come with the case controller factory-
installed in each case. 

 

7. 

Install new wires for the BACnet communications loop to 
each case controller in a daisy chain format. 

 

a. 

Follow the diagram in the 

BACNET DAISY 

CHAIN WIRING 

section.

 

8. 

New cases will need the MODBUS communication installed 
from case controller to case controller on the same circuit. 

 

a. 

Follow the diagram in the 

MODBUS NETWORK 

WIRING 

section of this instruction card.

 

9. 

Once the communications loops are installed, unplug the 
loop from the case controller and power up the device.

 

10.  The Visograph display will then need to be updated.

 

a. 

Press the 

UPDATE

 button on the display after 

booting it up. If not visible, move to the next step

 

11.  Each case controller will need the BacNET MAC Address 

and BacNET Device ID set at each Visograph. 

 

a. 

Follow the steps for addressing in the 

ADDRESSING 

section

 

of this instruction card.

 

12.  Once the Address is set, 

do not reboot the case controller; 

it will reboot on its own in 7 minutes. Wait for the case 
controller to reboot before moving forward. 

 

13.  Now plug in the comm. loop and go to the E2E to 

commission the case controller in the E2E. 

 

a. 

Refer to the 

COMMISSIONING 

section for 

instructions.

 

14.  Once the case controller communicates with the E2E, wait 

5 mins for the initial sync to take place. 

 

15.  At this point the cases should be running. 

 

16.  Verify that the XEV20 is communicating with the case 

controller and is addressed 2 and 3 if there are two 
XEV20Ds. 

 

a. 

EEPR control will always be on the (A) master 
case. 

 

17.  Once the case has been running for 10 to 15 minutes, the 

EEPR and EEV valves will need to be calibrated for the first 
time. 

 

a. 

Follow the steps in the 

EEPR AND EEV 

CALIBRATION SECTION.

 

BACNET DAISY CHAIN WIRING WITH THE E2 

 

MODBUS NETWORK WIRING 

 

MODBUS MASTER-SLAVE ADDRESSING 

1. 

On the master case controller main status screen, enter the 
main menu. 

2. 

Press the 2

nd

 button from the left for system configuration 

and then the first button at the next menu to select system. 

3. 

Make sure that the Standalone option is set to 

NO

 for 

controllers included in a master-slave lineup. 

4. 

Press the 5

th

 button from the left to arrow over to the 

Modbus parameters 

5. 

Configure the Modbus address of the controller. For master 
controllers, set the Modbus address to 1 and the addresses 
of the slave controllers to 0. For a slave controller, use 
addresses 2-6 and leave the other addresses S1-S5 to 0. 
Set the Modbus baud rate to 1

9200

6. 

After changes are made, wait for five minutes then reboot 
the case controller. 

 

iPro NexGen Quick Start Guide v1.7 

Reviews: